Page 91 - Untitled-1
P. 91

70 PROJECT LIFE CYCLES

Why, What, When, Who.

Current status of project.

Forecasts.

Status of key items.

Risk assessment.

Info pertinent to other projects.

Recommendations.

• Post-Mortem (Evaluation).

Scope Accomplished.

Technical Objectives Met.

Recommendations for other projects.

Project Historical Data.

• Other Closeout Items.

Final Measurements.                Sell Residuals.

Punch List.                        Transfer Residuals.

Uncompleted tasks.                 Toss Residuals.

Special Closeout Tasks.TEAMFLY     Document Transactions.

Final Report.                      Personnel Disposition and Reports.

Client Acceptance.                 Arrange for transfer or reassignment

Client Acceptance                  of dedicated resources.

Documents.                         Release assigned resources.

Client Feedback.                   Document performance.

Testimonials.                      “Atta-boy/atta-girl” letters.

Assets Disposition.                Archives.

Using Project Life Cycles

If the project life cycle is a phase-oriented view of the project, then it stands to
reason that we can and should use the project life cycle as one of the mecha-
nisms to monitor the project progress against the project goals. Often, but not al-
ways, there is a definable set of deliverables associated with each phase. We
should pause to review the project accomplishments, as each phase comes to
completion. This is one of the times during the project when we look at the ob-
jectives and evaluate performance to date against these objectives. If the objec-
tives are not being supported, should the strategy be changed? Should the
project be terminated? Should the objectives be re-examined? If the project
moves ahead, should new targets be examined and communicated? Should the
   86   87   88   89   90   91   92   93   94   95   96