Page 40 - GM E-Booklet Dec-2022
P. 40

4. Increase in Sectional Speeds and New lines / Doubling

               a.  Sectional Speeds

                 FM-DHNE Section – CRS sanction received for Raising of sectional speed from 100 to
                   110 Kmph on 02.12.2020 and same has been implemented.

                 SHNR –GLY (New Double Line) – Double line commissioned in the month of Sept’20
                   with  MPS  75  Kmph  and  increasing  of  speed  from  75  to  100  Kmph  implemented  in
                   March’21.

                 GWD  –  PASR  (27.36  Km)  between  Gadwal  –  Raichur  Section  –  The  sectional
                   speed has been increased from 60 Kmph to 100 Kmph on 14.08.2021.

                 RC – PASR (29.89 Km ) between Gadwal – Raichur Section – The sectional speed
                   has been increased from 50 Kmph to 75 Kmph in May’2022.

                 SHNR –GLY (New Double Line) –Increasing of speed from 100 to 110 Kmph, PCE
                   approval received on 27.10.2022 and implemented on 03.11.2022.

               b.  New Lines


                 Gajwel – Kodakandla – New line (11.529 Km) – CRS inspection done on 11.02.2022
                   and CRS sanction received for 60 Kmph.

                 Makthal-   Magnur stations, 13.305 Km – (Devarkadra - Krishna Section) has been
                   done in March 2022 and section commissioned.

                 Akanapet  -  Medak  stations,  17.338  Km  New  line  has  been  done  on 26.03.2022.
                   CRS sanction given for 70 Kmph.


               c.  Doubling


                 Falaknuma - Umdanagar– Double line (DN Line) (14 Km) – Commissioned in the
                   month of March’21, taken over by open line.

                 Umdanagar – Shadnagar - Double line (DN Line) (29.76 Km) – Commissioned in the
                   month of July ’21, taken over by open line.

                 Divitipalli – Mahabubnagar – Double Line (DN Line) (10.453 Km) – CRS inspection
                   done on 10.02.2022 and  CRS sanction received for 90 Kmph.

                 Gollapalli - Divitipalli stations – Double line (DN Line) 13.255 Km – Commissioned
                   in the month of March 2022 and taken over by open line.






                                                            38
   35   36   37   38   39   40   41   42   43   44   45