Page 175 - GM booklet 2019 test
P. 175
3. Level crossing works
3.1. Elimination of Manned Level Crossings.
Target 2019-20
Type of
Elimination PHOD Board Cumulative Progress
Direct Closure -
1 1
Diversion 1
(LC No: 148)
6
(LC No: 11, 21,56, 82, 101 on SC-
RUB 27 12
DHNE section, LC No: 239 on SC-
MUE section)
1
ROB 1 1
(LC No: 4 on GWD-RC section)
29 14 * 8
* Board‟s Target raised from 09 to 14 vide Hqrs letter no: W/287/LC/Tgt/Vol III Dt
29.10.2019.
4. Relaxation of Permanent Speed Restrictions.
Target 2019-20 = 03 (Boards Target = 01)
Progress = 01
The following PSR‟s are further planned for relaxation.
Existing PSR
Remarks
Sl
No Km Section SR Reasons
218/0- IKI-MOA- 75 Consolidation Planned for relaxation after completion
01
222/0 ALPR Kmph of Track of Formation Treatment work.
491/0- 60 4 D curve in
02 UPW-SCP Planned for relaxation to 75 Kmph.
492/0 Kmph Ghat section
152