Page 3 - P S - Engineering -final
P. 3
3. Track machine utilisation:
Sl No Type of Machine Target 2020-21 Progress up to Feb‟21
1 Tie Tamping Machine 1300 Km 1466 Km
2 Unimat 500 Pts 478 Pts
3 BCM 80 Km 76.00 Km
4. Level crossing works
Elimination of Manned Level Crossings.
Progress
Sl Description of Boards Internal
No item Target Target up to Remarks
Feb 21
Construction of
1 - - - -
Road Over Bridge
LC No: 18,26, 44, 49, 109, 112,
Construction of
2 Limited Height 10 12 14 119, 140 on SC-DHNE section, LC
No: 245, 232, 230, 224, 213, 208
Subways
on SC-MUE section
Closure of Level
crossings on
3 - - - -
account of
diversion of Traffic
Closure of Level
crossings on
4 - - - -
account of meager
traffic
5. Relaxation of Permanent Speed Restrictions.
Target 2020-21 = 02 Nos
Completed = 02 Nos
Existing PSR
Remarks
Sl
No Km Section SR Reasons
Relaxed to 100 Kmph in Jan‟2021
218/0- IKI-MOA- Consolidation of (Caution order of 04 Kms length has
01 75 Kmph
222/0 ALPR Track been made as caution order of 01
Km length)
491/0- 4 D curve in Relaxed to 75 Kmph in Feb‟2021
02 UPW-SCP 60 Kmph
492/0 Ghat section
139