10. USFD progress.


          USFD TESTING PROGRESS UPTO THE MONTH OF Feb-2021


                      Sl. No.                        Items                               Details
                         1      Total length to be tested/ Month                           244
                         2      Total yearly work load                                    2924
                        A       RAIL                                                      1990
                         a      Cumulative target upto the month                         1824.2
                         b      Progress during the month                                  203
                         c      Total progress up to the month                           1787.5
                        B       Bridge                                                     71
                         a      Cumulative target upto the month                           65
                         b      Progress during the month                                   0
                         c      Total progress up to the month                             71
                        C       High banks and cuttings                                    272
                         a      Cumulative target upto the month                           249
                         b      Progress during the month                                   0
                         c      Total progress up to the month                            175.5
                        D       Curves                                                     65
                         a      Cumulative target upto the month                           60
                         b      Progress during the month                                   0
                         c      Total progress up to the month                             43
                         5      Point &Xings, SEJ's and scabs                              146
                         a      Cumulative target upto the month                           134
                         b      Progress during the month                                 42.5
                         c      Total progress up to the month                             77
                        E       WELDS(AT/SKV+FBW)                                          380
                         a      Cumulative target upto the month                           348
                         b      Progress during the month                                  50
                         c      Total progress up to the month                             429
                         3      Total (A+B+C+D+E)                                         2924
                         a      Cumulative target upto the month                          2680
                         b      Progress during the month                                 295.5
                         c      Cumulative Progress upto the month                       2583.0