Page 31 - GM Booklet 06.03.2021
P. 31

7. Canal Crossing Works: Canal Crossing work between KEK-DAB stations on SC-MUE
            section is completed duly inserting the girder on 16.05.2020 and further removing the girder
            after completing the work of casting of box under the track on 29.07.2020.


















            8. Increase in Sectional Speeds and New lines.

               a.  Sectional Speeds

                 FM-DHNE Section – CRS sanction received for Raising of sectional speed from 100
                   to 110 Kmph on 02.12.2020 and implemented.

                 SHNR –GLY (New Double Line) – Line commissioned in the month of Sept‟20 with
                   MPS 75 Kmph and PCE approval received for increasing speed from 75 to 100 Kmph
                   on 03.02.2021, will be implemented by 31.02.2021.


               b.  New Lines

                 Jaklair – Makthal - new line (11 Km) – Commissioned in the month of June‟20, to be
                   taken over by open line from construction.

                 Manoharabad  –  Gajwel  -  new  line  (33  Km)  –  Commissioned  in  the  month  of
                   June‟20, to be taken over by open line from construction.

                 Shadnagar – Gollapalli – Double line (DN Line) (30 Km) – Commissioned in the
                   month of Sept‟20, taken over by open line.

            9. Special Achievements made in Track and Bridge works.

                 Progress of Deep Screening of Plain Track with BCM machine for the year 2020-
                   21 up to Feb-21 is 76 Km.

               i.  During the shadow block of 68 Hrs at Br No: 74 on SC-DHNE section, the Work of
                   Deep Screening with BCM machine has been carried out between stations KCG-FM
                   (DN Line) on SC-DHNE section and a progress of 2.590 Km has been achieved for
                   three days  (16.05.20 = 1.260 Km, 17.05.20 = 0.820 Km and 18.05.20 = .510 Km)

               ii.  On 27.12.2020, Division has achieved a progress of 2.700 Km of Deep Screening
                   with BCM machine on a single day (02 Machines), BCM 290 has achieved 1.200  Km
                   and BCM 394 has achieved 1.500 Km. The progress of 2.700 Km in a single day is
                   the best ever progress achieved in the Division.

                                                            21
   26   27   28   29   30   31