Page 2 - Electrical(Traction Distribution)
P. 2

9.  Checking of Turnouts and Crossovers With 2030 mm pantograph:

            As  per  the  Headquarters  Special  drive  No.  51  Dated:  05.11.2020,  All  the  Turnouts  and
            Crossovers should be checked with 2030 mm pantograph free movement in view of recent
            panto entanglements in other Divisions. Division has done Turnout and Crossover checking
            by fixing the 2030 mm panto on tower cars. In HYB sub-division, all the stations and major
            yards were checked with 2030 mm panto and defects were attended.


            II.    Special  Works carried out in HYB division:


                   a)  RVNL Railway Electrification works Staff were deputed at FM – SHNR, GWD – RC &
                       UR – MBNR sections for Erection of masts and DA‟s at FM –UR, GWD-RC sections and
                       for SED checking.


                   b)  Bifurcation of Power supply in Automatic territory 5 Nos. of 5 KVA A.Ts charged with
                       25KV OHE at RKO [ 1 no.], BOZ [2 nos.] & YKA-HPG [2 Nos] for non-blanking of Signals
                       to facilitate 230 V AC supply to S&T Goomties.


















                   c)  OHE modification work completed in view of “New Satellite Depot” at CVB/Yard.



















                                                                          OHE modification works at CVB yard

                   d)  Mock drill : was conducted by NDRF/GNT at BMO and OHE wires of RD-4, 5 slewed and
                       Re-slewed at BMO/Yard on 13.02.2021









                                                                                              Mock Drill at BMO