Page 3 - ELECTRICAL MAINTENANCE
P. 3

Energy Conservation Action Plan Targets by HQ for the year 2020-21


                                                                                     Target        Achieved
             S.    Item Description                                                  for the       upto
             No.                                                                     year
                                                                                     2021-22       Sep-21


             1     Provision of sanctioned Lifts                                     4             1


             2     Energy Consumption (w.r.t. last year)                             -5%           -9.92%

                   100% implementation of Energy Audit
             3                                                                       11            6
                   recommendations (No. of Audited Locations)


                   Bifurcation of fans in 2/3 circuits at stations to
             4     ensure switching off fans in non-seated areas                     10            7
                   during non-train hours


                   Provision of timers for Lighting & Fan circuits on
             5                                                                       10            7
                   Platforms

             6     Reassessing the contractual demand (CD) at actual  2                            1


                   Solar based street lights for a) Colonies b) Training
             7                                                                       20            16
                   Institutes etc.


                   Natural light pipe system in select workshops and
             8                                                                       5             12
                   service building

                   Energy Efficient pumps in place of old inefficient
             9                                                                       20            10
                   pumps


             10    Automation of Pumps                                               10            6


             11    Rewiring of Staff quarters                                        30            17


                   Use of occupancy sensors for light control in
             12    Officers chambers, Conference rooms, Waiting                      25            16
                   Halls, concourse area, SSE/JE's offices etc.


             13    Provision of smart metering in residential quarters   200                       786


                   Inverters AC's in place of non-star rated AC's
             14                                                                      100           30
                   excluding EESL quantity


                   BLDC Ceiling fans in place of non-star rated ceiling
             15                                                                      500           225
                   fans  excluding EESL quantity






                                                                                                   Page 3 of  3