Page 9 - Diesel_Loco_Shed(MLY)
P. 9

  40  HP  Booster  pump  has  been  provided  at  KCG
               station for quick watering for PF No. 1 & 2.







            Analysis of power factor using Power analyzer at various pumping installations.


             A special drive conducted to study and analyze the effect of pumping load on power factor
               of the system using power analyzer. Initially analyzed various parameters of GLR pump
               house at Rail Nilayam which is having 2 x 15 HP centrifugal pumps and 1 x 10 HP mono
               block pump and caters water supply requirement of RN building and colony area.
             From the analysis, to improve Power Factor, 10 KVAR capacitor has been provided for
               compensation.
             Drive  for  Thermal  Imaging  for  identification  of  hotspots  in  panels  is  also  started  from
               28.04.2020









                                              Thermal imaging for identification of Hot spots.

             3-Way  RMU  is  commissioned  at  Laundry  Substation  at
               Kacheguda Station.
               The details of RMU are as follows.
               Make: ABB
               No. of VCBs: 03
               Capacity: 630A
               No. of inputs: 01 - Connected to Incoming Supply.
               No. of outputs:  02 - Connected to TR1 & TR2.


             70Nos. of 150W LED lights provided for yard portal lighting
               at KCG Yard by Construction/SC. This resulted in increase
               in connected load of 10.50kW at KCG.