Page 3 - Summary of works
P. 3
HYDERABAD DIVISION
Status of Works (Abstract)
Total
Sl. PH Total No.of Works No.of Works in No.of Works in No.of Works in Dropped No.of Works
No Y-o-S Sanctioned Estimate Stage Tender stage Progress stage Works Completed No.of
Wks
PB / LS PB / LS PB / LS PB / LS PB / LS PB / LS
LAW WP DRM LAW WP DRM LAW WP DRM LAW WP DRM LAW WP DRM LAW WP DRM
2010-11 1 1
2015-16 1 2 1 2 3
P 2016-17 1 6 1 1 5 7
9 53
A 2017-18 1 1 1
2018-19 1 34 1 10 2 22 35
2019-20 6 6 1 1 3 2 5 12
Total Works 59 2 41 16 1 1 10 2 5 1 25 14 59
2009-10 2 1 1 2
2010-11 4 4 4
2015-16 1 1 1
O 2016-17 1 1 1 1 2
10 64 S 2017-18 1 1 1
W
2018-19 2 2 2
2019-20 2 2 2
2020-21 2 2 2
Total Works 16 1 7 8 2 2 1 1 3 7 16
2016-17 1 1 1 1 2
HRD 2017-18 1 1 1
11 65 &
Trg 2018-19 7 2 5 7
2019-20 5 2 5 2 7
Total Works 17 2 13 2 1 8 2 1 5 17
Grand Total 277 40 114 123 1 5 0 1 2 12 20 29 65 2 5 0 16 72 47 277