Details of  POWER BLOCKS Availed as on 28.02.2021

                 Power                       Availed     Hrs of Power     Hrs of Power       Percentage
                   Block         Asked                    Block Asked      Block Issued

                 TRD              310          310            461              461              100%
                 Local             0            0               0                0              100%
                 Block
                 Engg.            178          178            757              757              100%
                 RVNL              37           37            112              112              100%

          Plan Head:

                   The plan head expenditure for 3700 and revenue expenditure for TRD/HYB unit is submitted
           below:

                                       Primary
                        Allocation                   RG SL         Expenditure         Percentage
                                          unit

                        Revenue        PU 28          1537              794              51.65%

                                       PU 32          3406             2532              74.33%

                                    Primary                 Sanctioned        Expenditur     Percenta
                    Allocation                     BG
                                      unit                      Cost               e             ge

                      PH-3700        LSWP           1           22789              0             0%