Page 10 - CRS - Engg
P. 10
9.WELD POPULATION – SKV, FBW
WELD POPULATION
SECTION AT/SKV FBW
SC-DHNE 12074 33955
SC-MUE 36750 7298
JKM-BDHN 3115 292
MJF-STPD 2 0
MJF-MLY 33 49
GWD-RC 687 8268
DKC-KSN 245 4186
TOTAL 52906 54048
10. USFD progress.
USFD TESTING PROGRESS UPTO THE MONTH OF Sept-2021
Sl. No. Items Details
1 Total length to be tested/ Month 284
2 Total yearly work load 3410
A RAIL 1389
a Cumulative target upto the month 694.5
b Progress during the month 59.5
c Total progress up to the month 694
B Bridge 71
a Cumulative target upto the month 36
b Progress during the month 0
c Total progress up to the month 71
C High banks and cuttings 272
a Cumulative target upto the month 136
b Progress during the month 17
c Total progress up to the month 43
D Curves 65
a Cumulative target upto the month 33
b Progress during the month 33.5
c Total progress up to the month 43.5
5 Point & Xings, SEJ's and scabs 256
a Cumulative target upto the month 128
b Progress during the month 36.5
c Total progress up to the month 61.5
E WELDS(AT/SKV+FBW) 422
a Cumulative target upto the month 211
b Progress during the month 53
c Total progress up to the month 380
3 Total (A+B+C+D+E) 2475
a Cumulative target upto the month 1238
b Progress during the month 199.5
c Cumulative Progress upto the month 1293
Page 10 of 10