Page 53 - 2019 Supra Technical NMT
P. 53

Supra – Software update and control unit replacement
        Action plan – Final report







                                                                                                                                1     Service plan

                                                                                                                                2     Programming plan


                                                                                                                                3     Final report


                                                                                                                                4     Display action plan

                                                                                                                                5     Display operation report




                                                                                                              • Once the action plan has been fully

                                                                                                                  implemented, ISTA will display the ‘Final
                                                                                                                  report’ tab


                                                                                                              • Final report lists the actions carried out


                                                                                                              • Recommendation to Display and Print the

                                                                                                                  ‘Operations report’


                                                                                                              • End road test required to set up TPMS








      THE ACADEMY