260 FLOATING CONSTRUCTION
      • Insulation: site specific.
          - Installation: Loose lay on substrate.
          - Joints: Butted.
      • Separating layer: Polyethylene sheet minimum 125 micrometres thick (500 gauge).
          - Installation: Loose lay over insulation.
          - Joints: Lap and seal with tape to prevent penetration of self smoothing screed.
      • Edge strips at perimeter abutments: 5 mm thick resilient polyethylene foam.
          - Installation: To full depth of screed.
          - Joints in strips: Lap with separating layer and seal with tape.

BATCHING AND MIXING

303 AGGREGATES
      • Sand: To BS EN 13139.
          - Grading limits: In accordance with BS 8204-1, table B.1.

305 BATCHING AGGREGATES
      • Mix proportions: Specified by weight.
      • Batching: Select from:
          - Batch by weight.
          - Batch by volume: Permitted on the basis of previously established weight:volume
             relationships of the particular materials.
          - Gauge boxes: Accurate. Allow for bulking of damp sand.

310 MIXING TROWELLED SCREEDS
      • Mixing:
          - Mechanical mixer: Suitable forced action. Do not use a free fall drum mixer.
      • Materials: Mix thoroughly to uniform consistence.
      • Admixtures: Do not use other than the basic accelerator.
      • Water content: Minimum necessary to achieve crystallisation of synthetic anhydrite
          and full compaction.

315 MIXING SELF SMOOTHING SCREEDS
      • Dry preblended materials: Batch using completely full bags only.
      • Materials: Mix thoroughly to uniform consistence.
      • Water content: Sufficient to achieve correct flow rate for screed.
      • Flow rate test of mix batches:
          - Test method: Flow ring test.
          - Timing: Before pumping screed and at strategic intervals during screeding.
          - Criteria: Screed manufacturer's recommended values.
          - Results and frequency of testing: Record.

LAYING

325 LEVEL OF SCREED SURFACES
      • Permissible deviation (allowing for thickness of coverings): ± 5 mm from datum.

 326 SCREEDING TO FALLS                                               6118-AEW-XX-XX-NBS-A-01
       • Screed cover: Maintain minimum thickness at lowest point.
       • Falls: Gradual and consistent.
            - Gradient (minimum): site specific .

RotF generic (intermediate) NBS 2014