Page 184 - B6118-AEW-XX-XX-PP-A-0001_(P17)_Contractors Manual
P. 184

SUPPLY





       S1 Free issue / direct suppliers






       S1.3 Contractor Order Website



       McDonald’s have developed a bespoke                   The  system will automatically  direct order
       ‘ordering’  system  for  their  nominated  supply     enquiries to the designated supplier appointed
       chain items. Principal Contactors  & Project          for  the  particular product.  Where  multiple
       Managers  will be provided with system log in         suppliers are used Contractors  will need  to
       details to enable them to:                            select the correct  supplier  for the project as
       - Browse items and place orders  per project          notified  to  them  via  McDonald’s  Procurement
         (project information  is linked to  the EotF        (as highlighted in the EotF programme) or via
         Programme)                                          liaison with their Project Manager.
       - Browse items and place orders per decor
         scheme or restaurant area (so free shopping         Bespoke or  non-standard parts will  still  require
         in  any  concept  or  specific  area  such  as      offline  liaison  with  the  relevant  appointed
         externals, toilets or accessories)                  supplier for the particular concept.  Contractors
                                                             should liaise with their Project Managers or the
       It is envisaged that a project could be ordered       Procurement  Team  if they  are  unsure  which
       in one session however the system allows for:         suppliers to send enquiries to.
       - Orders to be placed into a saved ‘draft basket’
         without having to be completed immediately          Nominated  suppliers will politely refuse  orders
         until all requirements are captured                 via any  other  method  going  forward  as this
       - Multiple  orders to be placed  by project as        resource  should become  the  method  for
         required – so not holding up full orders if any     ordering products for McDonald’s projects.
         particular detail is subject to minor change
                                                             http://orders.mcdonaldsmandr.co.uk/login.
       The system utilises  the EotF programme  and          html
       will  issue  warning  notifications  to  Principal
       Contractors and McDonald’s Project Managers           Access  information  to  the  website  in  terms  of
       where  late order  placement  could jeopardise        usernames & passwords should have already
       the  critical path.  All enquiries made via the       been supplied.  If you require access & have
       ‘ordering’  system  will  be  confirmed  by  email    not yet had these details please contact Paul
       to  both  the  originator  of  the  enquiry  &  the   May (paul.may@uk.mcd.com) for more details.
       respective suppliers.

       Goods are invoiced either to McDonald’s  in
       the traditional manner or where a contractor is
       due to pays for goods (such as floor or ceiling
       products) they must add invoice details to be
       able  to  complete  the  enquiry.    The  ‘ordering’
       system will not deal with financial transactions
       but  will highlight the  possible order  values for
       the project for both McDonald’s & Contractors
       alike.




        S1.3           Contractor Order Website            2.0                        25 July 2017