Page 382 - B6118-AEW-XX-XX-PP-A-0001_(P17)_Contractors Manual
P. 382

CONSTRUCT





        C3 Shopfitting






        C3.20  Counter Ceiling Raft; Adaptations

        Where the menu boards are installed  using             The new downstand will generally be a MDF box,
        a ceiling mounted  cradle  (or  if it is impossible    200mm deep, projecting 118mm from the face
        to locate on the menu board bulkhead) then             of the existing raft. The exception to this sectional
        the ORB should located within a new, add on            detail occurs to suit the ORB as identified.
        section to the counter ceiling raft.
                                                               The  full new  downstand  and  existing  counter
        A  new  MDF downstand  will be bolted  to  the         ceiling raft  should be redecorated  white
        front  face of the  existing MDF counter  raft as      throughout.
        identified in the following details. It is imperative
        that the principal contractor check the existing
        unistrut  suspension  system  and  confirm  or
        upgrade this to suit the additional weight being
        added.





















































         C3.20          Counter Ceiling Raft; Adaptations   3.0                        02 November 2016