Page 22 - ROYAL VIEW BILLING REQUEST
P. 22
PHASE I & II – 40 out of 58 units COMPLETED
LGU (Lower Ground Floor)
CLUSTER CLUSTER CLUSTER CLUSTER CLUSTER CLUSTER
I & 9 2 & 6 3 & 7 4 & 10 5A & 5B 14 & 15
UNIT A UNIT B UNIT A UNIT B UNIT C UNIT D UNIT A UNIT B UNIT C UNIT D UNIT A UNIT B UNIT C UNIT D UNIT A UNIT B UNIT A UNIT B UNIT C UNIT D INSTALLED STATUS
Water heater 40/ 58 COMPLETED
CARPORT
• Water Meter 40/ 58 COMPLETED
• Hose Bibb 40/ 58 COMPLETED
LGF TOILET 40/58
• Shower ( w/ shower valve) COMPLETED
• Bibb trap 40/58 COMPLETED
• Water Closet 40/58 COMPLETED
• Tissue holder 40/58 COMPLETED
• Strainer & Cleanout 40/58 COMPLETED
• SERVICE SINK – Pop up drain and 40/58 COMPLETED
faucet
• WASHING AREA – Faucet 40/58 COMPLETED
• CARPORT – Hose Bibb 40/58 COMPLETED
STORAGE ROOM 40/58 COMPLETED
• Pendent sprinkler
LGF TO UGF
• Sidewall sprinkler 40/58 COMPLETED