Page 13 - Proposal Sinergi Pembangunan Sekolah Generasi Quran_UMKM
P. 13

CQF / SGQ / Proposal Pembangunan Sekolah Generasi Quran / 03-2022              13






                    Rencana Anggaran Biaya








             NO          URAIAN PEKERJAAN               BIAYA BAHAN        UPAH JASA        TOTAL BIAYA

              I.  PEKERJAAN PERSIAPAN (DIRECT COST)                                           126.321.737,20
              A.  PEKERJAAN PERSIAPAN                     49.626.820,54     76.694.916,67       126.321.737,20

              II.  PEKERJAAN ARSITEKTUR                                                     3.095.818.264,08

              A.  PEKERJAAN GALIAN & PASIR                 25.103.404,00    19.542.660,00      44.646.064,00
              B.  PEKERJAAN PASANGAN                       362.748.139,31  105.135.502,50      467.883.641,81
              C.  PEKERJAAN BETON PRAKTIS                  236.327.121,44   98.822.066,67       335.149.188,11
              D.  PEKERJAAN PLAFON                        48.702.230,56     37.598.625,00      86.300.855,56
              E.  PEKERJAAN PENUTUP LANTAI                288.505.257,84   155.878.958,75      444.384.216,59
              F.  PEKERJAAN FINISHING DINDING             184.233.732,50    64.900.728,21      249.134.460,71
              G.  PEKERJAAN PINTU & JENDELA               763.877.300,00   152.773.505,00     916.650.805,00
              H.  PEKERJAAN SANITAIR                       71.028.720,00    15.095.410,00       86.124.130,00

              I.  PEKERJAAN ATAP                           298.111.666,67   112.304.174,33     410.415.841,00
              J.  PEKERJAAN LUAR BANGUNAN                  22.693.361,30   32.435.700,00        55.129.061,30

              III.  PEKERJAAN STRUKTUR                                                      1.480.243.118,40
              A.  PEKERJAAN GALIAN DAN URUGAN              92.888.018,00                       92.888.018,00
              B.  BETON LANTAI 01                        1.053.035.867,75                    1.053.035.867,75

              C.  BETON LANTAI 02                          187.457.172,64                       187.457.172,64
              D.  RANGKA ATAP UTAMA                      146.862.060,00                       146.862.060,00

              IV.  PEKERJAAN MEKANIKAL & ELEKTRIKAL                                          615.593.240,00
              A.  INSTALASI PENERANGAN DAN KOTAK-KONTAK   190.487.000,00                      190.487.000,00
              B.  INSTALASI PASANG DAYA LISTRIK 23,000 VA  39.804.000,00                       39.804.000,00

              C.  INSTALASI KABEL TOUVUR DAN PANEL DAYA    13.321.800,00                        13.321.800,00
              D.  INSTALASI CCTV                         104.599.800,00                       104.599.800,00
              E.  INSTALASI PENANGKAL PETIR               22.242.200,00                        22.242.200,00
              F.  INSTALASI AIR KOTOR/ BEKAS DAN VENT CUP  56.972.800,00                       56.972.800,00
              G.  INSTALASI AIR BERSIH                    58.587.600,00                        58.587.600,00
              H.  INSTALASI AIR HUJAN                     46.669.000,00                        46.669.000,00
              I.  INSTALASI TATA UDARA                    82.909.040,00                        82.909.040,00


                                                TOTAL                                        5.317.976.359,68
                                           DIBULATKAN                 -                -     5.317.000.000,00
                                    JASA KONSTRUKSI 10%                                       531.700.000,00
                                          GRAND TOTAL                 -                -   5.848.700.000,00