Rencana Anggaran Biaya
NO URAIAN PEKERJAAN BIAYA BAHAN UPAH JASA TOTAL BIAYA
I. PEKERJAAN PERSIAPAN (DIRECT COST) 126.321.737,20
A. PEKERJAAN PERSIAPAN 49.626.820,54 76.694.916,67 126.321.737,20
II. PEKERJAAN ARSITEKTUR 3.095.818.264,08
A. PEKERJAAN GALIAN & PASIR 25.103.404,00 19.542.660,00 44.646.064,00
B. PEKERJAAN PASANGAN 362.748.139,31 105.135.502,50 467.883.641,81
C. PEKERJAAN BETON PRAKTIS 236.327.121,44 98.822.066,67 335.149.188,11
D. PEKERJAAN PLAFON 48.702.230,56 37.598.625,00 86.300.855,56
E. PEKERJAAN PENUTUP LANTAI 288.505.257,84 155.878.958,75 444.384.216,59
F. PEKERJAAN FINISHING DINDING 184.233.732,50 64.900.728,21 249.134.460,71
G. PEKERJAAN PINTU & JENDELA 763.877.300,00 152.773.505,00 916.650.805,00
H. PEKERJAAN SANITAIR 71.028.720,00 15.095.410,00 86.124.130,00
I. PEKERJAAN ATAP 298.111.666,67 112.304.174,33 410.415.841,00
J. PEKERJAAN LUAR BANGUNAN 22.693.361,30 32.435.700,00 55.129.061,30
III. PEKERJAAN STRUKTUR 1.480.243.118,40
A. PEKERJAAN GALIAN DAN URUGAN 92.888.018,00 92.888.018,00
B. BETON LANTAI 01 1.053.035.867,75 1.053.035.867,75
C. BETON LANTAI 02 187.457.172,64 187.457.172,64
D. RANGKA ATAP UTAMA 146.862.060,00 146.862.060,00
IV. PEKERJAAN MEKANIKAL & ELEKTRIKAL 615.593.240,00
A. INSTALASI PENERANGAN DAN KOTAK-KONTAK 190.487.000,00 190.487.000,00
B. INSTALASI PASANG DAYA LISTRIK 23,000 VA 39.804.000,00 39.804.000,00
C. INSTALASI KABEL TOUVUR DAN PANEL DAYA 13.321.800,00 13.321.800,00
D. INSTALASI CCTV 104.599.800,00 104.599.800,00
E. INSTALASI PENANGKAL PETIR 22.242.200,00 22.242.200,00
F. INSTALASI AIR KOTOR/ BEKAS DAN VENT CUP 56.972.800,00 56.972.800,00
G. INSTALASI AIR BERSIH 58.587.600,00 58.587.600,00
H. INSTALASI AIR HUJAN 46.669.000,00 46.669.000,00
I. INSTALASI TATA UDARA 82.909.040,00 82.909.040,00
TOTAL 5.317.976.359,68
DIBULATKAN - - 5.317.000.000,00
JASA KONSTRUKSI 10% 531.700.000,00
GRAND TOTAL - - 5.848.700.000,00