Page 16 - Statement of Qualifications - Haley Edit 3
P. 16
RLC EXPERIENCE
Greenfield, MA – 1.5 MW Axio Green photovoltaic
project 13.8 kV distribution system impact
analysis
P
ittsfield, MA – 1.5 MW Silver Lake photovoltaic
project – 23 kV distribution system impact analysis
P
ittsfield, MA – 2.0 MW Pittsfield Sanitary District
photovoltaic project – 23 kV distribution system
impact analysis
G
eorgia Mountain, VT – 10 MW wind project –
conceptual and detailed design of 34.5 kV collection
system and interconnection
owell, VT – 42 MW wind project – conceptual design
L
of 34.5 kV collection system and interconnection
L
owell, VT – 63 MW wind project – preliminary and
detailed design of 34.5 kV aerial and underground
collection system, collector substation and upgrades
to other local 46 kV substations
R
utland, VT – 85.5 MW wind project – conceptual
design of 34.5 kV collection system and
interconnection
earsburg, VT – 45 MW wind project – preliminary
S
design of 34.5 kV collector system and 69/34.5 kV
collector substation
S
heffield, VT – 40 MW wind project – transmission/
interconnection testimony on system impact
Bristol, NH – 80 MW wind project – Conceptual
design of 230 kV interconnection substation and
34.5 kV collector system
F
erdinand, VT – 91 MW wind project – Conceptual
design of 115 kV interconnection substation and
34.5 kV collection system
Canada
Norway, PEI – 9 MW wind project – detailed design
and construction management of 34.5 kV collector
system and 69/34.5 kV collector substation
West Cape, PEI – 99 MW wind project – detailed
design and construction management of 34.5 kV
collector system and 138/34.5 kV collector substation
Mont Copper, Quebec – assessment of 34.5 kV
collector system
16 STATEMENT OF QUALIFICATIONS STATEMENT OF QUALIFICATIONS 17