Page 11 - Statement of Qualifications
P. 11
RLC SERVICES
Millyard Substation
The Millyard Substation project included retiring the existing
34.5 – 4.16 kV substation and building a new substation on the
adjacent property. The new substation included two new 34.5-
4.16 kV, 10 MVA transformers, two new 34.5 kV circuit breakers,
and one new 4.16 kV metalclad switchgear, including relaying and
battery systems. RLC created the Detailed Engineering documents
required to construct the project.
MEPCO 392,396 & 3001 Structure Replacement
The MEPCO Project was for the design of replacement structures
for three, 345 kV transmission lines. The lines stretch 127 miles
and include over 1000 structures. In addition to the structure
replacement design, RLC also developed a design criteria
document to specify present and future transmission system
modification design requirements. Deliverables included
construction documents, construction specifications, material list
and plan and profiles.
South Meadow Breaker Replacement
RLC provided design services for the replacement of thirty-eight,
23 kV oil circuit breakers. The work also included the replacement
of twenty-one each disconnect switches as part of the Bus
Rehabilitation and nine Relay Replacements. RLC developed
all design documents required for construction. Construction
support services were provided along with as-built documents.
Rehabilitation and nine Relay Replacements. RLC developed all
design documents required for construction.
Capital Investment (Estimating Services)
RLC provides a complete portfolio of estimating services ranging
from level 1 to 4 for all major design discipline activities. Services
range from basic scoping to complete system upgrade detailed
Estimates of Probable Cost. Our clientele include Renewable
Energy Developers, Utilities and Independent System Operators.
RLC is well versed in all major Northeast utility estimating
procedures along with ISO-NE’s Procedure 4, and +- 50%/25%
Estimate of Probable Cost process.
Facilities Studies
RLC continuously performs studies to identify equipment and
related costs necessary to design, engineer, procure, construct,
install, test and commission the subject Project and Project’s
Network Upgrades Facilities (NUF) necessary to reliably
interconnect to the Transmission Owner’s system. RLC works
with the subject Project’s Developer and Connecting and Affected
Transmission Owner(s) to ensure the Project is performed in
accordance with the Scope of Work.
10 STATEMENT OF QUALIFICATIONS STATEMENT OF QUALIFICATIONS 11