Page 14 - Graypvine December 2020
P. 14

PROJECT SPOTLIGHT

























                Project Diamond:
     14



                Next-level E-commerce






            A bird's-eye view of Amazon Project Diamond in Little Rock, Arkansas.


              In November of 2019, the Southeast Office           of these facilities. That experience gave the team
            was awarded its second AR Sort Facility for the       the confidence in the schedule and an approach
            e-commerce giant, Amazon.com. The LIT1 facility,      that was focused on those robotics and material
            known as “Project Diamond”, is located in Little      handling systems. It was clear in the planning stages
            Rock, Arkansas and is the largest project ever        of the proposal that this previous experience, as well
            built for Amazon. The facility is approximately 3.8   as some innovative construction methods, would
            million s.f. and five stories tall, reaching nearly 100   make the Gray proposal a hard one to walk away
            feet in elevation just a mile from Arkansas’s largest   from. As expected, the team delivered a solid and
            airport. The facility houses a very complex system    successful proposal. The schedule was aggressive,
            of conveyors, robots, racks, shoots, spirals and      the team was lean, and the plan included a couple
            vertical lifts that allow that package you ordered on a   “out-of-the-box” ideas that had everyone interested.
            Tuesday to arrive at your house on Wednesday! We      Randy Benningfield and Matt Brown have led the
            are certain that the unanimous decision to award      charge on site while Brad Heberling and Daniel
            this facility to Gray was not solely because of the   Scarpelli run point on the Project Management front.
            proposal and presentation, but also in large part     This is a team that quickly gained the cohesiveness
            because of our team’s incredible performance on the   necessary to carry out that bold plan presented in
            first AR Sort Facility — Project Crowne in Bessemer,   late 2019.
            Alabama. Since winning Project Diamond, Gray has        I want to highlight a couple of those “out-of-the-
            been awarded two more of these AR Sorts, located      box” construction methods that gave the team
            in Augusta, Georgia and Detroit, Michigan.            not only a higher rate of production but a ton
              Project Crowne provided Gray the knowledge          of flexibility – flexibility that would allow them to
            of Amazon’s robotic and material handling             overcome adverse weather, changes in scope, and
            installation process, which is the heart and soul     other unforeseen circumstances, but still provide the