Page 51 - ECLECTIC MARCH-2022 INSIDE PAGES_p2.indd
P. 51
t Chowbhaga area Tangra area

Here we have implemented our project in Overhead We have implemented our project in Overhead mode
mode with co-axial cable. Total 7 nos DTRs were covered with co-axial cable here. The network reorganization job
in this project. Total length of the circuit is 3410 meter. was carried out at D. C. Dey Road, Tangra and Govinda
Khatick Road area comprising of the LT network of 18 nos
Figure 10: Mini Pilar Box for UG network DTRs. Total length of the circuit is 3000 meter.
The loss level before implementing the scheme was
around 25.79% and after completion of project the loss The loss level before implementing the scheme was
was around 7.51%..Total lost MU saved was 1.77 MU. around 33.08% and after successful completion of project
the loss was reduced substantially. Total lost MU saved
Narkeldanga North Road area was 2.63 MU.

We have here implemented our project in Overhead Table 1: Comprehensive Loss Reduction Chart
mode with co-axial cable for 9 nos of DTRs. Total length
of the circuit is 900 meter. Project area % Loss Co-axial Lost Unit
The loss level before implementing the scheme was before Cable Saved
around 54% and after successful completion of project project Drawl (MU)
the loss was substantially reduced. Total lost MU saved execution (ckt. KM)
was 3.55 MU.
West Chowbhaga 25.79% 3.41 1.77
Darapara area
Narkeldanga North 54% 0.9 3.55
We have implemented our project in Overhead mode with
co-axial cable here. The network reorganization job was Road
carried out at Darapara area comprising of the LT network
of the 2 nos. DTRs. Total length of the circuit is 750 meter. Darapara 52.14% 0.75 1.63
The loss level before implementing the scheme was around
52.14% and after successful completion of project the loss Tangra 33.08% 3 2.63
was substantially reduced. The lost MU saved was 1.63 MU.
Total 8.06 9.58

CONCLUSION

Though co-axial cable is a proven technology in the
telecommunication field but in the field of distribution
of electricity it is yet to be proven. So we had executed
POC before implementation of pilot projects. The main
challenge was to drawl of co-axial cable along with
termination at newly designed junction box. However,
we have managed to develop the fittings for drawl
along with junction box. After success in POC, we have
implemented several pilot projects and we got expected
results. So the new technology relevant to our business
was introduced successfully. We have decided to replace
existing overhead network with co-axial cable in pilfer
prone areas where illegal abstraction takes place from
overhead main line.

After successful implementation of POC with
underground network, UG coaxial cable will be drawn in
near future.