Page 191 - ADMINISTRATIVE MANUAL
P. 191

172


                   e)  Clarify  that the specifications and other terms in the bidding documents are minimum
                       requirements;
                   f)  Reiterate  and  emphasize  the  importance  of  confidentiality  during  the  bid  evaluation
                       process, and the applicable sanctions and penalties;

               The holding of a pre-procurement conference may not be required for small procurements, i.e.,
               procurement of infrastructure projects costing five million pesos (P5,000,000.00) and below;

                   II.    Advertisement/Posting

                   a)  For contracts above P5 Million
                       1)  Advertised at least twice within a minimum period of 14 cd, within a minimum period
                          of six (6) cd between publications, in a newspaper of general nationwide circulation
                          which  have  been  regularly  published  for  at  least  two  (2)  years  before  the  date of
                          issuance of the advertisement;
                       2)  Posted continuously in the website of the procuring entity concerned;
                       3)  Posted in the G-EPS during the two-week period;
                       4)  Posted at any conspicuous place reserved for this purpose in the premises of the
                          procuring entity.

                   b)  For contracts P5 million and below
                       1)  Posted continuously in the website of the procuring entity concerned;
                       2)  Posted in the G-EPS during the two-week period
                       3)  Posted at any conspicuous place reserved for this purpose in the premises of the
                          procuring entity.

               For infrastructure projects, the bidding documents shall be issued within thirty (30) calendar days
               from last day of period of advertising and/or posting of invitation to Apply for Eligibility and to Bid,
               and the opening of bids shall be conducted within the following periods from the last day of the
               issuance of the bidding documents.

                           Estimated Contract Cost                                Period
                                  (in pesos)
                 Up to twenty five (25) million                15 to 30 calendar days
                 Above twenty five (25) million up to fifty (50)  15 to 45 calendar days
                 million
                 Above fifty (50) million up to two hundred (200)  30 to 60 calendar days
                 million
                 Above two hundred (200) million               60 to 90 calendar days


               In case of simple or repetitive or standardized works where time is of the essence, the head of
               the procuring entity may reduce  the above term of issuance to not less than fifty percent (50%)
               of the periods indicated above.

               Provided, however, that the periods for conducting eligibility check, pre-bid conference and the
               issuance of the bidding documents shall be followed: