Page 199 - ADMINISTRATIVE MANUAL
P. 199

180


               The BAC shall modify the terms, conditions and specifications in the first bidding documents,
               when  necessary,  to  change  the  scope  of  work  or  to  adjust  the  procurements  entity’s  cost
               estimates or specifications. However, the BAC shall be maintained. All bidders who have been
               declared eligible in the first bidding shall be allowed to submit new bids. The BAC shall observe
               the same process and set the new periods according to the same rules followed during the first
               bidding.

               Should there occur a second failure of bidding, the procuring entity concerned may enter into a
               negotiated procurement.

                   VIII.   Award of Contract

               Award of contract shall be made to the bidder with the Lowest Calculated Responsive Bid, as its
               submitted bid price or its calculated bid price, wherever is lower.


               Performance Security


                                                                          Minimum Amount in % of
                                Form of Security                            Total Contract Price
                  Cash, certified check cashier’s check,                        Five percent
                  manager’s check, back draft or irrevocable                        (5%)
                  letter of credit.
                  Bank guarantee                                                Ten percent
                                                                                   (10 %)
                  Surely bond                                                  Thirty percent
                                                                                   (30 %)
                  Foreign government guarantee                             One hundred percent
                                                                                  (100%)



               Warranty

                                     Defects/Liability Period                          Warranty Period


                   __________________________            __________________________
                                                  1 Year                                       2 to 15 Years

                  Project                                Final
               Completion                           Acceptance

               For the procurement of infrastructure projects, the contractors shall assume full responsibility for
               the contract work from the time project construction commenced up to final acceptance by the
               government and shall be held responsible for any damage or destruction of the works except
               those occasioned by force majeure. The contractor shall be required to put up a warranty security
               in the form of cash, bank guarantee, letter of credit, Government Service Insurance System bond,
               or callable surely bond.
   194   195   196   197   198   199   200   201   202   203   204