Additional considerations for infiltrating soils

         ■  Discharge to protected waters or protected groundwater (e.g. SSSI or SPZ’s) may require
          additional treatment stages and liaison with the environmental regulator.

         ■  More general discharge to groundwater (usually infiltrating soils) can be referenced in table
          26.4 of the SuDS Manual.                                                                                 Concept Design

         ■  Medium pollution hazard level developments will require risk screening to determine

          appropriate mitigation measures. Refer to table 26.5 and 26.6 of the SuDS Manual

         ■  For developments of a high pollution hazard level a detailed risk assessment will be required.



        Typical diffuse urban pollution concentrated at
                                   a conventional gully.

















                                                                                                                   38




                                                             Linear swales alongside an entrance path at this
                                                                                     infiltration SuDS project,
                                                                                      Burlish Primary School.