Page 79 - Oxford City SuDS DESIGN & EVALUATION
P. 79

Responsibility
       Deliverable      Key design points                  Key evaluation points
                                                                                             to check
       hydraulic        Drawings should confirm            Sensibility check to be           LLFA
       calulations &    volumes provided and refer back  performed to ensure that
       drawing          to hydraulic analysis              sufficient storage is provided to                       Detailed Design
       volumes          requirements.  Drawings            meet hydraulic calculations.
                        references / annotations should
       match
                        clearly relate to calculations.
       Designers        To consider construction,          Demonstrate safe design for       LPA & LLFA
       hazard & risk    maintenance / operation by         users and operatives of the

       assessment.      personnel and day to day site      scheme.
                        use by public.
       Long sections  Cross sections should not use        Review in general, side slopes    LPA & LLFA
       and cross        exaggerated vertical scales to     and depths shown.
       sections         allow proper understanding of
                        how scheme will actually look
       Planting         Outline any SuDS specific          Ensure plants from accredited     LPA & LLFA
       design &         planting requirements.             source to minimise risk of

       schedule                                            invasive species.
       Landscape        Integrate SuDS within the wider    Check that the SuDS network is    LPA & LLFA
       design           landscape design                   accessible, multifunctional and
       drawings                                            contributes to the overall
                                                           landscape quality.
                                                                                                                   74
       Consents &       Vary and can include: discharge    Check that relevant consents are  LPA & LLFA &
       permits          consents; offsite works & 3rd      in place or can be obtained in    EA & IDB &
                        party access consent. The list of   principle.                       WASC
                        required consents may be initially
                        defined at pre-app discussion.
       Maintenance      Key plan (1 side of A4) detailing   Maintenance type & cost is       LPA & LLFA
                        the maintenance regime and         appropriate & proportionate and
                        identifying key maintenance        features are easily accessible.
                        locations such as outlets and      Design achieves passive
                        flow control locations.            maintenance where possible.
       Adoption         Confirmation of commitment to      Review that sufficient safeguards  LPA, LLFA,
       arrangements     adopt aspects of the scheme        are in place for the long term    WaSC &
                        being offered for adoption.        maintenance and operation of      Highways & IDB
                        Confirmation of ownership and      the drainage. Consider the        & WASC
                        maintenance responsibilities for   potential impact of replacement
                        all parts of the SuDS scheme       of propriety products.
                        which are not being adopted.






      Oxford City Council SuDS D & E Guide                                                                    © 2018 McCloy Consulting & Robert Bray Associates
   74   75   76   77   78   79   80   81   82   83   84