Source Controls providing collection &
      conveyance

      Water must either be kept at or near the

      surface to allow runoff to flow into SuDS
      structures, or it must be collected through                                                                  Detailed Design
      permeable surfaces.

      The simplest method of collection of runoff
      from an impermeable surface is to intercept it
      as sheet flow from a hard surface. Where
      runoff flows directly from hard surfaces to
      filter strips or swales then runoff must leave
      the hard surface effectively without the risk
      of ponding.
                                                                       Pershore High School, Worcestershire.
         ■  swales                                             Low risk access road with 1.2m wide filter strip
                                                                        source control and conveyance swale.
         ■  filter drains





      Site Controls

      Where runoff is collected at the surface, a

      depression in the ground, mimicing hollows in                                                                124
      the natural landscape, is the easiest and most
      cost effective way to manage large volumes                       Pershore High School, Worcestershire.
      of water in the landscape.                                 Swale conveyance into pond site control for
                                                                                  final treatment and storage.
      Where landscape is limited, storage
      opportunities within  pavements and on roofs
      should be explored.

      Careful design can maximize opportunities
      with different design volumes in different
      places providing maximum opportunities for
      multi-functional use and biodiversity.

         ■  basins

         ■  wetlands

         ■  ponds


         ■  storage structures