Page 85 - Luton SuDS DESIGN & EVALUATION
P. 85

9.5.4.3  Making allowances for interception losses

      As a rule of thumb, where the total wetted
      area of SuDS components equates to at least
      25% of the development area (all buildings
      and hard surfaces) then it is acceptable to                                                                  Detailed Design
      make an allowance for interception losses.
                                                              For more detailed analysis methods
      This loss can be applied within storage
      calculations by reducing the rainfall depths            see SuDS Manual Section 24.8
      by 5mm.




      9.5.4.4  Defining infiltration rates


      The specified infiltration test methodology            For example, tests should not be undertaken
      should be representative of the proposed               1.5m below ground level when shallow
      design.                                                infiltration is proposed from permeable
                                                             pavement, rain gardens or basins which will
      The depth of water and depth of test trench
                                                             be located close to ground surface.
      below ground level should seek to replicate
      the attributes of the proposed infiltration
      system.

                                                                   Bromsgrove Civic Centre re-development.         80
                                       Permeable block and slab paving with a central grass detention basin
                                                          provide a fully integrated infiltrating SuDS scheme.



































      Luton Borough Council SuDS D & E Guide                                                              © 2018 McCloy Consulting & Robert Bray Associates
   80   81   82   83   84   85   86   87   88   89   90