Approach 2
Where volumes cannot be managed to
predevelopment status, then outflow rate Detailed Design
should be controlled to a maximum of Qbar
rate (which is equivalent to a 1 in 2 year or
Qmed which is used by FEH methods) for all
rainfall return periods up to the 1 in 100 year
rainfall event plus climate change allowance.
This is the approach most commonly utilised
by industry at present due to simplicity of
analysis, but can result in a greater storage
requirement due to more restricted outflow
rates. (NSTS S6)