Page 16 - October2019_BarJournal
P. 16

FEATURE REAL ESTATE LAW



        MAY PARTIES NEGOTIATE



        PUBLIC CONSTRUCTION CONTRACTS

        AFTER THE AWARD?







                  BY TERESA G. SANTIN




                          hat  is  a  public  doing, does the public entity violate the law?   as Ohio courts analyze bid defects and a public
                          entity to do if, upon   Does the public entity have any discretion?   entity’s discretion to waive them in the same or
                          awarding a contract   What if the contractor was by far the best   similar way as they analyze negotiations after
                          through the public   among the competition in an area where there   bids are opened or after a contract is awarded.
        W bidding                   process,  are few options? What if the public entity   The courts have analyzed modifications made
        the contractor asks to negotiate some of that   faces a deadline that would be put at risk by   prior  to  bid  opening,  after  bid  opening, and
        contract’s  terms?  Should  it  take  a  hard  line,   continued negotiations?   after an award.
        refuse to negotiate, and risk damaging its   On the flip side, what if a contractor believes   With these principles in mind, a
        relationship with the contractor? Should it   that it absolutely must ask for modifications   “substantial” deviation or modification of a
        take the path of least resistance and agree to   after the award? What if it identified some   contract post-award impermissibly affords
        some or all of the contractor’s requests? In so   major risks only after it submitted its bid?   the winning bidder a competitive advantage.
                                            What if it found a mistake that, absent a   A modification is substantial if it affects the
                                            correction, immediately renders the project   amount of the bid and affords a bidder an
                                            unprofitable? What if it learned that the   advantage not allowed to the other bidders.
                                                                                 Numerous Ohio courts, but not all, have
           Niki Z. Schwartz                 supplier  of  the  critical  equipment  has  gone   permitted insubstantial modifications in the
                                            out of business? Will it put itself in jeopardy
              Mediator/Arbitrator           by asking for a change?            context of a variety of topics.
                                              Competitive bidding laws seek to create   •  A contractor’s request for permission to
                                            an honest and fair mechanism for awarding   switch to a subcontractor different from
                                            public contracts. Through a sealed bid process,   the one identified in its bid, so long as that
                                            a public entity should select the winning bidder   change did not alter any legal obligations
                                            based on merit and price alone. Competing   within the public contract, has been found
                                            bidders all base their bids on the same designs,   to constitute an insubstantial modification.
                                            specifications, and contract documents. Once   In that case, the change occurred after bid
                                            bids are  opened,  each bidder’s qualifications   opening, but prior to an award.
                                            and prices are sealed no more and become   •  In another Ohio case, the court construed a
                                            public knowledge. Thus, the general legal view   winning bidder’s failure to include the price
                                            in Ohio is that modifying contract terms after   of one  line item to mean that the bidder
                                            bid opening could impair the sanctity of the   would do that work at no cost and that this
             “If he can settle              sealed bid process and otherwise undermine   failure did not afford the winning bidder
                                                                                 a competitive advantage. Thus, that court
                                            open and honest competition, which protects
               a prison riot,               the public and other bidders from favoritism   found that the public entity at issue could
                                                                                 waive this bid irregularity after bid opening.
                                            and fraud.
                he can settle                 Not much case law exists in Ohio analyzing   •  Another court determined that an
                 anything!”                 the propriety of post-award negotiations. Ohio   insubstantial modification, post-award,
                                                                                 may include allowing additional time to
                                            case law concerning the selection of the lowest
                                            and best bidder, or lowest responsive and   complete various stages of the work, such as
                                            responsible bidder, in the competitive bidding   more time to assume control of operations
                                                                                 on a project.
                 216-696-7100               process is analogous and instructive, as is   •  Likewise,  the  same  Ohio  court  found  that
                                            case law involving negotiations following the
             nzs.adr@gmail.com              opening of bids, but prior to an award. This case   permitting a contractor, post-award, to park
                                            law appears to be somewhat interchangeable,   vehicles on publicly owned property free of
      16 |  CLEVELAND METROPOLITAN BAR JOURNAL                                                    CLEMETROBAR.ORG
   11   12   13   14   15   16   17   18   19   20   21