AfrElec                                      NEWS IN BRIEF                                            AfrElec








                                                                                  The ruling also set the important legal
                                                                                principle that Eskom is only obliged to supply
                                                                                electricity to paying customers.
                                                                                  “The Electricity Regulation Act of 2006
                                                                                entitles Eskom to interrupt electricity supply
                                                                                to a non-paying customer and in this matter;
                                                                                Eskom had taken proper preliminary steps
                                                                                and due process which did not entitle the
                                                                                applicant to the interim interdict.”
                                                                                  The court also held that Eskom’s
                                                                                interruptions of supply to the defaulting
                                                                                municipality were important and necessary
       Nigeria’s NERC says discos          their service commitment or not. And   for its survival.
                                                                                  “Pioneer had an available internal remedy
                                           consumers will be compensated for failure
       will compensate electricity         to deliver on that service. We do not expect   which entailed lodging a dispute with the
                                           consumers to start putting gadgets to monitor
                                                                                National Energy Regulator of South Africa
       consumers for power                 electricity.”                        (NERSA).”
                                                                                  The court held that before an aggrieved
       failures                                                                 party approached it for relief against Eskom;
                                                                                it should demonstrate that it first exhausted
       The Federal Government has warned power   ESKOM                          the internal remedies contemplated by the
       distribution companies (Discos) that they will                           Electricity Regulation Act by approaching
       compensate affected consumers for defaulting   Eskom welcomes high court   NERSA.
       in service delivery if they fail to supply the                             “The relationship between Eskom and
       required quantum of electricity under the new   ruling on defaults       the municipality is reciprocal in that Eskom
       service reflective tariff regime.                                        supplies bulk electricity against payment.”
         According to a report from Punch, this   Eskom has welcomed what it deems as a   Eskom has committed to ramping up its
       disclosure was made by Sanusi Garba, the   landmark judgment after the High Court   effort to collect the unpaid municipal debt to
       Vice Chairman of Nigerian Electricity   affirmed the utility’s right to terminate   improve its own coffers.
       Regulatory Commission (NERC), who   electricity supply to defaulting, non-paying
       doubles as a commissioner at the commission,   customers.
       in Abuja. He said that NERC had deployed a   The South Gauteng High Court handed
       mechanism to monitor the Discos.    down the judgement on October 13.    GAS-FIRED GENERATION
         NERC had revealed that all Discos    Eskom said it was now in a position
       committed to delivering agreed quantum   to enhance all its collective efforts from   Siemens gets Mozambique
       of power to customers in various categories   defaulting municipalities that collectively owe
       beginning from September 1, 2020, when   the utility more than ZAR31bn in overdue   LNG turbines job
       the new service reflective tariff regime   debt.
       started. The commission is expected to start   Pioneer Foods brought the case against   Siemens Energy said it has won a contract
       monitoring the Discos on a monthly basis   Eskom seeking to review and set aside Eskom’s  to supply power generation equipment and
       to ensure compliance by the power firms in   2018 decision to interrupt electricity supply   boil-off gas compressors for the Mozambique
       terms of meeting the agreement.     to the Walter Sisulu Municipality due to its   LNG project.
         He said the service reflective tariff, which   failure to pay for electricity supplied in terms   CCS JV, a joint venture between Saipem
       took effect on September 1, 2020, before it   of the municipality’s agreement with Eskom.  and McDermott awarded the contract.
       was suspended for 14 days after an agreement   “The court ruled that Pioneer Foods   The facility is being developed in the Cabo
       between the Federal Government and labour   had no standing in the electricity supply   Delgado province on Africa’s East Coast.
       unions, would ensure that customers of   agreement between Eskom and the   The project, led by Total E&P Mozambique
       distribution companies paid for what they   municipality, and dismissed the application   Area 1, includes the development of offshore
       consumed.                           with costs,” said Eskom in a statement on   gas fields in Mozambique’s Area 1. It also
         Garba said, “The commission has come   Wednesday.                      includes a liquefaction plant with a capacity in
       forward to say tariffs will be service-based,   According to the power utility, Pioneer   excess of 12mn tonnes per year.
       meaning that you will pay your rates in   Foods is a customer of the municipality, and   As part of the contract, Siemens Energy
       correlation with the level of service you get.   as such had no legal right to bring the case   will supply six SGT-800 industrial gas
       Now, obviously, the commission has its own   against Eskom to court.     turbines. The units will provide low emissions
       mechanism for monitoring the performance   “This is a landmark judgment affirming   onsite power generation. The 54MW turbine
       of the Discos. This is because if a Disco says   the validity and lawfulness of Eskom’s rights,   rating selected for this project has a gross
       you are in Band C, it means the Disco is   powers and entitlement to invoke section   efficiency of 39 percent, Siemens Energy said
       committed to giving you between 12 to 16   21(5) of the Electricity Regulation Act of   in its statement on Thursday.
       hours as a minimum.                 2006 to interrupt the supply of electricity to a   It features a robust, dry low-emission
         “So the role of the commission is to   delinquent customer, in this case, the Walter   (DLE) combustion system that enables ‘world-
       monitor and at the end of the month to   Sisulu Municipality in the Eastern Cape,”   class’ emission performance over a wide load
       determine which Disco has complied with   Eskom said.                    range.



       P10                                      www. NEWSBASE .com                         Week 41  15•October•2020
   5   6   7   8   9   10   11   12   13