Page 18 - EurOil Week 36
P. 18

EurOil                                 PROJECTS & COMPANIES                                            EurOil























       Equinor suffers Castberg



       setbacks





        NORWAY           EQUINOR has suffered setbacks at the Johan  to the Hammerfest LNG plant. The com-
                         Castberg oilfield in the Barents Sea, potentially  pany last week awarded a contract to Stavan-
       The FPSO will be   meaning the project could slip behind schedule.  ger-based Aibel for front-end engineering
       delayed due to      In a statement on September 2, Norway’s  design (FEED) work at the liquefaction
       corrective work.  Petroleum Safety Authority (PSA) said it had  complex.
                         launched a probe into problems with the hull   Valued at NOK140mn ($1.7mn), the con-
                         of the field’s floating production storage and  tract covers designs for an onshore compres-
                         offloading (FPSO) unit. PSA said that Equinor  sion unit and Hammerfest LNG’s potential
                         had identified major challenges with the qual-  electrification. The compressor will provide
                         ity of the hull’s welds. It also said errors had  pressure support to maintain production
                         been found in the analysis programme used for  levels at the plant. This will be important as
                         fatigue calculations.                well pressure at Snohvit decreases. The unit
                           Corrective work means that the FPSO hull  will also help boost overall recovery from the
                         will be delayed, PSA said.           field.
                           The FPSO hull was ordered by Equinor back   Equinor and its partners Petoro, Total, Nep-
                         in 2017 from Singapore’s Sembcorp Marine. Its  tune Energy and Wintershall Dea aim to select a
                         construction was described at the time as “the  concept for the unit in this autumn.
                         most time-critical delivery” for the project to   The group is also considering electrifying
                         arrive on schedule. The field was originally  Hammerfest LNG to reduce emissions. This
                         scheduled to start up in late 2022 but Equinor’s  will involve the replacement of the plant’s gas
                         website now forecasts the launch in 2023.  turbines with power from shore, potentially
                           “Furthermore, efforts to correct weld and  bringing carbon emissions to near zero. A
                         fatigue analysis errors create uncertainty about  concept is due to be selected by the end of the
                         the structure’s integrity over the producing life  year.
                         of the field,” it said.                Final investment decisions (FIDs) on both
                           Equinor’s plan is to produce oil from the  schemes, collectively known as the Snohvit
                         FPSO for 30 years.                   Future project, are targeted for the second half
                           PSA said its investigation aimed to find out  of 2021. Aibel’s FEED contract has an option for
                         why the weld faults and analysis errors had not  engineering, procurement, construction and
                         been spotted earlier, in order to learn lessons for  installation (EPCI) work.
                         the future.                            “With the Snohvit Future project we aim to
                           Castberg, comprising three discoveries made  ensure future value creation from the Snohvit
                         in 2011, 2012 and 2014, is estimated to hold  field and to deliver on our ambitions for emis-
                         between 400 and 650mn barrels of proven oil. Its  sion reductions in Norway,” Equinor said in a
                         budget is NOK50bn ($5.6bn), after Equinor was  statement. “The Snohvit field contains enough
                         able to halve it by taking advantage of low costs  gas to maintain production beyond 2050, and
                         after the 2014 oil price crash. Equinor has a 50%  Hammerfest LNG will secure jobs for many
                         stake in the project, while partners Var Energi  years to come.”
                         and Petoro hold 30% and 20%.           Snohvit is one of only two fields in production
                                                              in the Barents Sea, the other one being the Goliat
                         Plans at Hammerfest                  oil deposit. It came on stream when the 7.6bn
                         Castberg is around 100 km north of  cubic metre per year Hammerfest LNG started
                         Equinor’s Snohvit field, which supplies gas  operations in 2007. ™



       P18                                      www. NEWSBASE .com                      Week 36   10•September•2020
   13   14   15   16   17   18   19   20   21   22