       Gazprom Neft pushes ahead




       with new oil project




        RUSSIA           RUSSIA’S Gazprom Neft has launched full-scale  pipeline system.
                         development at a group of oil sites in Western   Some 54 wells have already been sunk at
       Output at Zhagrin is   Siberia’s oil heartlands of Khanty-Mansiysk and  Alexander Zhagrin, and the count should reach
       expected to peak at   Tyumen, the producer announced on July 29.  920 by 2028, most of which will be horizontal.
       130,000 bpd by 2024.  The five licence blocks – Zapadno-Zimny,   The North-Vayskoye and Srednevayskoye
                         Yuzhno-Zimny, Severo-Vaysky, Karabashsky-84  fields, named after their respective blocks, hold
                         and Srednevaysky – span over 5,000 square km  594mn barrels of liquids hydrocarbons, while the
                         and are estimated by Gazprom Neft to hold  Yuzhno-Zimny and Karabashsky blocks could
                         650mn tonnes (476mn barrels) of oil in place  contain more than 132mn barrels of oil. Zapad-
                         (OIP). West-Zimny contains the Alexander  no-Zimny is assessed as comprising 2.84bn bar-
                         Zhagrin oilfield, which is already under develop-  rels of crude.
                         ment, with output slated to peak at 6.5mn tonnes   Prospecting work will continue at Seve-
                         per year (130,000 barrels per day) by 2024.  ro-Vaysky, Srednevaysky and Zapadno-Zimny
                           Alexander Zhagrin holds around 814mn  until 2027, and until 2029 at Yuzhno-Zimny and
                         barrels of OIP, according to Gazprom Neft. Dis-  Karabashsky-84. This will enable Gazprom Neft
                         covered in 2017, the field now hosts well pads,  to draw up development plans.
                         oil-gathering lines, a separation unit, an initial   “The Alexander Zhagrin field was brought
                         energy complex, power supply lines and a road  into development in just two years following its
                         transport network. An oil processing facility is  discovery – against an industry average of eight
                         due to be commissioned in 2022.      to 10 years,” Gazprom Neft’s deputy CEO for
                           Full completion of its oil transportation infra-  upstream, Vadim Yakovlev, said in a statement.
                         structure is anticipated by the end of this year.  “Going forward, this new hydrocarbon cluster in
                         These pipelines will link future oil treatment  south-west Khanty-Mansiysk will prove a solid
                         facilities with the Demyanskoye delivery point,  base for maintaining oil production volumes in
                         where crude will be fed into Russia’s national  this region.” ™