AfrElec                                             GRID                                              AfrElec







       Uganda to import emergency





       power from Kenya







        ZIBABWE          UGANDA has scheduled power cuts across the   Meanwhile, the government plans to import
                         country after its 183MW Isimba hydropower  60MW of electricity from neighbouring Kenya
                         plant was forced to suspend operations due to  to help make up the difference and plans to
                         flooding that affected generators and turbines,  restart an idled 50Mw thermal plant in Kam-
                         Minister of Energy and Mineral Development  pala, she said in a statement. An additional
                         Ruth Nankabirwa said on Tuesday (August 17).  20MW will come from Kakira sugar plant,
                           The hydropower plant, which is under an  which produces power from cane pulp.
                         emergency shutdown, represents 15% of the   With about 40 power plants, Uganda’s total
                         power generated by Uganda, East Africa’s  installed generation capacity has grown from
                         third-largest economy.               400MW in 2000 to 1,237MW as of October
                           Authorities will take a number of measures,  2020, 80% of which is from hydropower. Peak
                         including implementing load shedding, to min-  demand is about 800MW, according to the
                         imize demand on the grid, Nankabirwa said  regulator.™
                         until the plant is back online, which will likely
                         take several weeks.