       Equinor launches probe into “dramatic”




       Hammerfest LNG fire





        NORWAY           NORWAY’S Equinor has opened an internal   The probes by Equinor and the PSA “will be
                         probe into the “dramatic” fire that broke out on  important in identifying measures that will pre-
       Safety authorities   September 28 at its Hammerfest LNG facility on  vent similar incidents from happening again,”
       and the police are   Melkoye Island.                   Rummelhoff said. “We will support the investi-
       also investigating the   No personnel were injured in the afternoon  gation and the police investigation where there
       incident.         incident, and the fire was extinguished by emer-  is a need for it.”
                         gency services later that night. But Norway’s   Hammerfest LNG, which liquefies up to
                         Petroleum Safety Authority (PSA) has said it is  5.6mn tonnes per year (tpy) of gas from the off-
                         intending to investigate the “extremely serious”  shore Snovhit field, was shut down after the fire
                         and “frightening fire.”              broke out.
                           “The incident at Hammerfest LNG this week   “We are now working to map the extent of
                         was serious ... We are glad that no one was injured  damage after the fire and will then thoroughly
                         in the fire or in fighting it,” Equnor’s vice-presi-  review the technical integrity of the facility,”
                         dent of marketing, midstream and processing,  Rummelhoff continued. “Safety comes first,
                         Irene Rummelhoff, said on October 2. “The fire  and we will use the time we need to ensure a safe
                         was dramatic, especially for employees, suppliers  start-up.”
                         and neighbours in Hammerfest.”         The PSA inspected electric systems and
                           Both Equinor and PSA are trying to clarify  major accident preparedness at the facility in the
                         the course of events and establish the causes of  week before the fire. On September 24, the safety
                         the incident, and the police have also launched  regulator told Equinor that it had observed that
                         an investigation.                    some issues had not been satisfactorily followed
                           Prior to the fire Equinor was already investi-  up by Equinor since a similar audit was last car-
                         gating a gas leak that occurred in mid-Septem-  ried out in 2017.
                         ber at the facility.                   “Equinor takes the PSA’s feedback seriously
                           “Although there is no indication of a connec-  and has already started examining the basis for
                         tion, Equinor will also investigate if the fire can in  the findings to address pending items while we
                         any way be related to the leak,” the state-owned  wait for the PSA’s final report from the inspec-
                         company said. The investigation will also seek to  tion,” the company said. “We will also evaluate
                         determine if the power outage in Hammerfest on  whether the findings are isolated cases or if there
                         September 28 had a connection to the fire.  is a need to address routines and systems.” ™



       Week 40   08•October•2020                www. NEWSBASE .com                                             P19
   14   15   16   17   18   19   20   21   22   23