        Uzbek GTL project reaches



        91% completion





        UZBEKISTAN       UZBEKISTAN’S $3.6bn gas-to-liquids (GTL)  ended after Energy Minister Alisher Sultanov,
                         project has reached 91% completion, the coun-  Kashkardarya regional governor Zoiyr Mirzayev
       The ministry confirmed   try’s energy ministry reported on October 24,  and other top government were sent to the con-
       the plant was still   with some 12,000 workers now back on site after  struction site to try to quell tensions.
       on track for a 2021   coronavirus (COVID-19) disruptions over the   Uzbekistan’s economy has suffered a sharp
       launch.           summer.                              downturn as a result of the COVID-19 crisis,
                           Some 9,000 workers were evacuated from  and companies have complained about delays in
                         the site in July after an outbreak of COVID-  payments from Uzbekneftegaz (UNG) and other
                         19. The ministry’s latest progress report comes  state-owned enterprises. UNG is the operator of
                         after thousands over workers employed by  the GTL plant.
                         Enter Engineering, a key contractor at the   The project is among several flagship invest-
                         project, began a riot earlier this month over  ments in Uzbekistan aimed at converting the
                         unpaid wages, lengthy shifts and problems  country’s gas into higher-value products. The
                         with the serving of meals, according to local  ministry reiterated that the plant was scheduled
                         media reports. Those workers have now been  for completion in 2020, with production due to
                         paid and authorities have agreed to shorten  start in 2021. At full capacity, the plant will be
                         their shifts.                        capable of processing 3.6bn cubic metres per
                           Some workers told RFE/RL that the Uzbek  year of gas into 1.5mn tonnes per year (tpy) of
                         National Guard, security troops and the police  kerosene, diesel, naphtha and LPG. The products
                         were brought in to break up the riot. The unrest  will all be consumed by local industry. ™