Page 17 - MEOG Week 30.indd
P. 17

MEOG                                        NEWS IN BRIEF                                             MEOG

























       but repeatedly delayed, Al-Zour will be the   become ready to transmit gas from these   for operation,” Motamed said.
       largest integrated refinery and petrochemicals   platforms to the refinery on the coast.  Phase 13 of South Pars gas field is aimed
       plant in Kuwait.                       As reported by the portal of Pars Oil and   at the production of 56 mcm of gas, 75,000
         Al-Zour’s production capacity is estimated   Gas Company (POGC), which is in charge of   barrels of gas condensate, and 400 tons of
       at 615,000 barrels per day, increasing Kuwait’s   developing the giant field in the Persian Gulf,   sulfur per day in addition to one million tons
       overall refining capacity to over 1.5 million   the two 32-inch pipelines are each 100 km   of ethane and one million tons of propane and
       barrels a day.                      long and will transfer gas from the mentioned   butane per annum.
         KIPIC, a subsidiary of the Kuwait   platforms to be processed at the phase 13   South Pars is divided into 24 standard
       Petroleum Corporation, appointed a unit of   refinery.                   phases of development in the first stage. Most
       U.S. multinational Honeywell International   According to Phase 13 Operator Payam   of the phases are fully operational at the
       last year to provide technology and   Moatamed, the mentioned platforms were   moment.
       production systems for Al-Zour.     installed back in February and the project   The huge offshore field, shared with
         KIPIC was set up to manage refinery,   for connecting them to the pipelines was   Qatar, covers an area of 9,700 square km,
       petrochemicals and LNG import operations at   immediately started.       3,700 square km of which, called South Pars,
       the Al-Zour complex south of Kuwait City.  Moatamed also noted that the pipelines of   are in Iran’s territorial waters in the Persian
       REUTERS                             the 13B and 13D, the other two platforms of   Gulf. The remaining 6,000 square km, called
                                           the phase, were inaugurated back in February   North Dome, are situated in Qatar’s territorial
                                           2019.                                waters.
       GAS                                    All stages of the project including pipe   The field is estimated to contain a
                                           coating, installation engineering, seawater   significant amount of natural gas, accounting
       SP phase 13 transmission            piping, and commissioning of these lines have   for about eight percent of the world’s reserves,
                                           been done by Iranian experts and engineers,
                                                                                and approximately 18 billion barrels of
       pipelines ready to go               according to the official.           condensate.
                                              “Considering the need for group work of
                                                                                TEHRAN TIMES
       operational                         the operations, we managed to complete the
                                           project by observing the social distance in
       The gas transmission pipelines of South   such a way that while maintaining the health
       Pars gas field’s 13A and 13C platforms have   of the workforce, the pipelines became ready

































       Week 30   29•July•2020                   www. NEWSBASE .com                                             P17
   12   13   14   15   16   17   18