Page 14 - AsiaElec Week 41 2022
P. 14

AsiaElec                                           COAL                                              AsiaElec









       India suspends environmental





       clearance for coal power plant







        INDIA            INDIA’S National Green Tribunal has sus-  project not commissioned.
                         pended the environment clearance granted for   While dismissing the pleas by the appellant
                         the Yadadri thermal power station (TPP) being  agency, the Conservation Action Trust, related to
                         built in Nalgonda district.          the issue of forest clearance and conduct of pub-
                           The tribunal said that the project’s coal link-  lic hearing, the tribunal, however, found force in
                         ages, meaning its coal supply contracts, were not  the submission that there was no specific doc-
                         yet secure enough and that the project site was  ument for the coal linkage, except some MoUs.
                         too close to the Amrabad Tiger Reserve.  The 5 x 800-MW super-critical plant was
                           However, the Southern Zonal Bench of the  initially pitched with a proposal to use imported
                         Apex Green Court has given nine months for  coal blended with indigenous coal, and outlined
                         the Telangana State Power Generation Corpo-  in the environmental impact assessment submit-
                         ration, the project’s promoter, to get the project  ted to the Expert Appraisal Committee.
                         reappraised by the Expert Appraisal Committee.   BHEL is developing the machinery and pol-
                         It could then apply again for fresh clearance from  lution control mechanism that will have to be
                         the Ministry of the Environment and Forests  adopted for the mix.
                         (MoEF).                                During the course of arguments, however,
                           The ruling comes as India plans to cut gener-  it was submitted before the court, that total
                         ating output from a minimum of 81 coal-fired  indigenous coal was being opted for in view of
                         power plants by 2025 in an effort to replace ther-  the import restrictions imposed by the central
                         mal generation with cheaper renewables.  government.
                           India expects the plan to reduce power gen-  Considering the fact that the impact of the
                         eration by 58bn kWh from the 81 utility com-  coal on the ambient air quality would depend on
                         panies to save 34.7mn tonnes of coal and cut  the nature of coal used, the tribunal issued direc-
                         carbon emissions by 60.2mn tonnes, the latter  tions for further study in case 100% indigenous
                         said.                                coal is opted, and a reappraisal by the EAC.
                           The decision comes as international coal   Noting wide variation between the reports
                         prices have risen and the government has put  of Vimta Labs and the IICT with regard to mer-
                         pressure on coal importers to buy in more coal  cury content in the coal, which had not been pre-
                         in a bid to meet domestic demand for electricity.  sented before the EAC, the tribunal commented
                           In May, three India state governments said  that unless it is evaluated, a conclusion cannot
                         they will buy in 10.5mn tonnes in the near future  be reached.
                         in a bid to combat power cuts, potentially tight-  Noting that the exact distance between the
                         ening global coal markets and pushing up prices.  boundary of the project area and the Amrabad
                           The Indian government used powers under  Tiger Reserve has been given neither in the
                         the Electricity Act to require all power plants  report by the PCCF & chief wildlife warden, nor
                         reliant on imported coal to run at full capacity  in the EIA report, the bench noted that it was
                         until October 31 in a bid to boost power gener-  not possible to reach a conclusion as to whether
                         ation capacity.                      a clearance from National Board for Wild-
                           Construction work at the power station will  life is needed unless the distance is accurately
                         be allowed to go on during the appeals process,  measured.™
                         provided that the plant is not installed and the















       P14                                      www. NEWSBASE .com                        Week 41   12•October•2022