EurOil                                 PROJECTS & COMPANIES                                            EurOil



























       Romania urges OMV Petrom to submit overdue



       documents on Neptun Deep project





        ROMANIA          ROMANIA’S agency for mineral resources   The document should have been prepared
                         (ANRM) has asked OMV Petrom, the operator  based on the mineral resources agency ANRM’s
       Bucharest has asked   of the Neptun Deep offshore project, to submit  order 101/1997, Romgaz argued in its letter –
       the company to submit   the complete documentation for the Declaration  also citing the opinion of ExxonMobil, the for-
       documentation for   of Commerciality (DoC) regarding the depos-  mer operator of the Neptun Deep project, a role
       the declaration of   its covered by the project, CursDeGuvernare.ro  taken over by OMV Petrom after ExxonMobil
       commerciality for the   reported on January 4, quoting sources within  sold its 50% stake to Romgaz.
       project.          the government, familiar with the developments.   In case ANMR requests the said document
                           OMV Petrom should submit the documents  (under order 101/1997), OMV Petrom should
                         within six weeks, or the concession contract can  complete it (and not outsource it) based on exist-
                         be terminated, according to the publication. The  ing studies and send it to authorities as soon as
                         DoC submitted on December 13, a couple of  possible, Romgaz recommended.
                         weeks before the December 31 deadline, does   OMV Petrom has submitted the DoC already
                         not include the evaluation study of geological  (after it received an extension of the deadline),
                         resources and reserves for Domino and Pelican  yet is saying that a so-called Financial Invest-
                         Sud, the two deposits covered by the project, the  ment Decision (FID) would be taken sometime
                         sources reportedly explained.        in H1 next year. But Romanian legislation does
                           Reportedly, the evaluation study should  not include such an FID, which is a mere internal
                         detail the size of the reserves and the planned  procedure of the company, Romgaz argued.
                         calendar of production – a detail OMV Petrom   According to Romgaz, the initial draft of the
                         keeps postponing while expecting better regula-  DoC proposed by the former operator (Exxon-
                         tory terms from the authorities.     Mobil) and sent to the current operator (OMV
                           The DoC is the indispensable stage for start-  Petrom) “was made taking into account the
                         ing investments, and failure to submit it may  fact that the provisions of the concession agree-
                         result in the withdrawal of the operating license  ment should be regarded in the context of the
                         for the perimeter.                   Romanian legislation in force (ANRM’s order
                           Romanian state-controlled natural gas com-  101/1997)” – meaning it included the document
                         pany Romgaz also argues OMV Petrom should  detailing the resources, the calendar of invest-
                         have already set the calendar for Neptun Deep.  ments and production.
                           Romgaz, the junior partner in the 50:50 joint   The document mentioned by Romgaz is a
                         venture with OMV Petrom for Neptun Deep off-  technical and economic study for the assess-
                         shore project, reportedly argued that its partner  ment of resources and reserves and should
                         should have already submitted to authorities,  include: concrete start dates for investments;
                         along with the DoC,  a document (most likely the  clear production and economic profiles related
                         evaluation study requested by ANRM) detailing  to deposits declared commercial; geological
                         the existing resources and the calendar of the  maps executed in accordance with the require-
                         investments and production.  A letter originat-  ments of the legislation; all data missing from
                         ing from Romgaz on this topic was published by  the studies submitted as annexes (necessary
                         the government and published by Profit.ro on  for ANRM in order to confirm resources and
                         December 29, but it was quickly withdrawn.  reserves). ™