AsiaElec                                     RENEWABLES                                             AsiaElec


       Indian grids gearing up for all-





       important move to renewables









        INDIA            NEW Delhi has given the green light for a mul-  in place between the current financial year and
                         ti-billion US dollar project to help ready the  the end of FY2025-2026.
                         nation’s regional and national power grids for   Costs will be in part borne by India’s Central
                         an eventual move to linking with the increasing  Financial Assistance (CFA) programme to offset
                         number of renewable energy sites around the  Intra-State transmission fees in a bid to help keep
                         subcontinent.                        final user power costs down.
                           Already taking steps to promote its COP26   Crucially in such a large nation with five
                         commitments of reaching net zero by 2070,  regional grids supplying electricity to over 1bn
                         authorities in India are looking to supply 50%  people, multiple projects included in the overall
                         of its overall energy needs using current and  costing are aimed at preventing any overload of
                         exploratory renewable sources, while also  the nation’s critical electricity load management
                         increasing non-fossil fuel generation by the end  system as managed by India’s state-run Power
                         of the current decade – an estimated total of 500  System Operation Corp. Ltd (Posoco).
                         GW if achieved.                        In the short term it is understood the project
                           In the same time frame the government of  will supply 24 GW to the wider grid by the end
                         Narendra Modi is seeking to reduce overall car-  of the calendar year.
                         bon emissions by around 1bn tonnes, according   At present, the sub-continent had almost
                         to reports.                          158 GW of installed renewable and non-fossil
                           In a statement released on its website,  fuel capacity; around 40% of the nation’s total
                         India’s Ministry of New and Renewable Energy  installed electricity generating capacity.
                         (MNRE) announced: “The Green Energy Cor-  Hydropower makes up the bulk of this total,
                         ridor Project aims at synchronising electricity  coming in at 51.34 GW, with solar and wind gen-
                         produced from renewable sources, such as solar  eration projects accounting for a further 48.55
                         and wind, with conventional power stations in  GW and 40.03 GW respectively.
                         the grid.”                             Furthermore, India also generates close to 6.8
                           Local media indicate one of the first steps in  GW of electricity capacity from nuclear power
                         this transition is an ongoing project to connect a  plants (NPPs).
                         total of 20 GW to regional grids and ultimately   Overall, nationwide, total capacity generation
                         the national grid across seven of India’s most  is forecast to rise by a further 16 GW in the next
                         populous states.                     12 months.
                           The MNRE also announced that “The Cab-  As interest continues to grow in Indian
                         inet Committee on Economic Affairs, chaired  renewables after several years of stagnation
                         by the Prime Minister, Shri Narendra Modi, has  because of drops in return on investments, and
                         approved the scheme on Green Energy Corridor  lack of profit on feed-in tariffs (FiTs), reports
                         (GEC) Phase-II for Intra-State Transmission Sys-  now indicate a further 63 GW of renewable
                         tem (InSTS) for (the) addition of approximately  project capacity is currently under construction
                         10,750 circuit kilometres (ckm) of transmission  around the country.
                         lines and approx. 27,500 Mega Volt-Amperes   Foreign direct investments (FDIs) account
                         (MVA) transformation capacity of substations”  for a total of $7.3bn as of mid-2021, with 11% of
                         and that these transmission facilities will be put  the total coming in the last year alone. ™