       Jask Oil Terminal ready for action





        IRAN             FOLLOWING last week’s completion of phase  last week, following the announcement by the
                         one of the Goreh-Jask oil pipeline, Iran’s new oil  country’s oil minister that the conduit had been
                         terminal on the Sea of Oman is now 98% com-  completed.
                         plete and is ready to begin receiving, transferring   The pipeline will carry crude from the oil-
                         and exporting crude.                 fields in the West Karoun cluster, linking the
                           Speaking to press during a visit to the facil-  Gulf port city of Goreh in Bushehr province to
                         ity, Mohammad Meshkinfam, CEO of Pars Oil  the Omidieh pumping station, then on to the
                         and Gas Co. (POGC), the state firm developing  Bahregan and Jask terminals for onward export.
                         the project, said that the single-point mooring   Phase one of the 42-inch (1,067mm) 1,000-
                         (SPM) is operational.                km pipeline will provide for the transportation
                           The unit has a design throughput capacity of  of 460,000 bpd and 254,000 bpd of heavy and
                         1mn bpd and was installed 6km offshore Jask  light Iranian crude, respectively. Crude will be
                         for loading tankers with two 36-inch (914mm)  moved directly from the North Azadegan, South
                         pipelines laid during February linking it to the  Azadegan, Yadavaran, and Darkhovin oilfields,
                         shore.                               while supply from North Yaran will be moved to
                           Jask port will also feature an initial 20 stor-  a facility at Jofair before onward transportation
                         age tanks with a total storage capacity of 10mn  to the West Karoun station and beyond.
                         barrels of crude, with plans in place to expand   Phase 2 is also underway, which will increase
                         export the infrastructure and storage capacity to  the capacity of the line to more than 1mn bpd.
                         30mn barrels. It is being developed on an area of   The wider project will include five pumping
                         0.6 square km at a cost of around $305-315mn.  stations, two pigging stations and terminals.
                           Meshkinfam alluded to the strategic location   Karbasian noted that crude began flowing to
                         of the terminal, saying: “Iran has achieved a spe-  Jask on May 19 and will fill the facility’s crude
                         cial position outside the Persian Gulf and can  storage units, adding that the transportation of
                         now export oil from the Oman Sea for the first  crude from Goreh to Jask was a national plan and
                         time with the aim of reducing dependence on the  “the largest project in the oil industry”.
                         Strait of Hormuz and making it easier for foreign   He said the inaugural volumes would take
                         customers to access its oil shipments.”  “less than a month” to reach Jask, at which point,
                           Around 90% of exports are currently loaded  a new national plan will be inaugurated in a cer-
                         at the Kharg Island terminal and must pass  emony attended by President Hassan Rouhani.
                         through the Straits of Hormuz and the same goes   With that in mind, Meshkinfam said:
                         for imports.                         “According to the plans, from now on we are
                           Meanwhile, National Iranian Oil Co. (NIOC)  ready for receiving, transporting and loading
                         CEO Mehdi Karbasian said that oil had begun  crude oil by export tankers from the coast of
                         flowing through the $1.1bn Goreh-Jask line  Makran.”™