Page 9 - LatAmOil Week 01 2022
P. 9

LatAmOil                                         GUYANA                                            LatAmOil



                         The vessel is currently in the process of being   has submitted both documents and is awaiting
                         hooked up and commissioned, it noted.  review from the relevant government authori-
                           On the other hand, it said, the Payara project   ties and regulatory bodies.
                         is still slated to come on stream in 2024. The hull   Equity in the Stabroek project is split between
                         of the Prosperity, the FPSO that will be used to   ExxonMobil Guyana, the operator, with 45%;
                         support development at that field, has already   Hess Guyana Exploration, with 30%; and China
                         been completed and the vessel’s topsides are now   National Offshore Oil Corp. (CNOOC), with
                         under construction, it stated.       25%. The partners brought Liza-1, their first
                           Meanwhile, it added, ExxonMobil Guyana   development project, on stream in December
                         has drawn up the field development plan (FDP)   2019. They aim to launch Liza-2, the second
                         and the environmental impact assessment (EIA)   development project, this year, followed by
                         for Yellowtail, its fourth development target. It   Payara in 2024 and Yellowtail in 2025. ™



       CGX confirms plan to continue



       drilling Kawa-1 exploration well






                         CANADA’S CGX Energy has confirmed that it   and to potential deep-lying discoveries in Guy-
                         will move ahead with drilling work at Kawa-1,   ana’s offshore Stabroek block, the eastern end of
                         an exploration well at the Corentyne block off-  which is directly north of Corentyne.
                         shore Guyana, despite reports that the initiative   The partners had originally hoped to begin
                         was being wrapped up.                drilling Kawa-1 in early 2020, just a few months
                           Daniel Turpin, a spokesman for the com-  after PGS Geophysical (Norway) finished a 3D
                         pany, informed OilNOW.gy in late December   seismic survey over a 582-square km section of
                         that CGX and its Canadian partner Frontera   the northern part of Corentyne in November
                         Energy were proceeding with work at Kawa-1.   2019. However, PGS did not finish processing
                         He was responding to the news service’s report   the new data until June 2020, and they did not
                         on a notice dated December 24 from Guy-  spud the well until August of last year.
                         ana’s Maritime Administration Department   Equity in the Corentyne project is divided
                         (MARAD), which said that the partners were   between CGX, with 66.67%, and Frontera, with
                         winding down operations at the well site.  33.33%. Frontera is the majority shareholder in
                           “Contrary to your article ... drilling activities   CGX. ™
                         continue on the Kawa-1 well,” Turpin stated.
                         “There are currently no demobilisation activi-
                         ties underway.”
                           He did not say when CGX and Frontera
                         expect to finish drilling the well. However,
                         MARAD published a new notice on Decem-
                         ber 31 stating that the companies expected to
                         continue working for more than a month. “This
                         operation is scheduled to conclude on February
                         5, 2022,” the department reported.
                           Frontera had said earlier in December that
                         the partners had already sunk Kawa-1 to about
                         90% of its planned depth and that the data
                         collected thus far suggested the presence of
                         an active hydrocarbon system. It also noted,
                         though, that work on Kawa-1 was taking longer
                         than anticipated and that the cost of drilling
                         the well was set to rise from $80mn to $115-
                         125mn as a result. The partners may have to seek
                         additional financing and are exploring several
                         opportunities, it said, without elaborating.
                           CGX and Frontera are drilling Kawa-1
                         at a site that is around 200 km from shore in
                         355-metre-deep water. They hope the well’s
                         target Santonian and Campanian layers will be
                         analogous to the finds made at Block 58 offshore
                         Suriname, located directly east of Corentyne,   CGX is using the Maersk Discoverer to sink Kawa-1 (Photo: Maersk Drilling)



       Week 01   06•January•2022                www. NEWSBASE .com                                              P9
   4   5   6   7   8   9   10   11   12   13   14