       Egypt, Sudan express “deep concern”




       about Ethiopia’s filling of the GERD




        POLAND           EGYPTIAN and Sudanese official have stated   Ethiopia’s opposition to US involvement is
                         their deep concern about Ethiopia’s proposed  also caused by new US sanctions against Addis
                         filling and operation of the Grand Ethiopian  Ababa, imposing visa restrictions on Ethiopian
                         Renaissance Dam (GERD) this summer without  and Eritrean officials accused of crimes related to
                         first reaching a binding legal agreement.  the six-month conflict in Tigray region.
                           Egyptian and Sudanese ministers met this   The region has seen bloody armed conflict
                         week in Khartoum and said that they had held  between the Ethiopian government and the
                         positive talks as the two sides shared identical  Tigray People’s Liberation Front (TPLF).
                         views about Ethiopia’s actions.        Meanwhile, Addis Ababa said that it had fol-
                           The two countries stressed that they wanted  lowed the spirit of the African Union (AU)-spon-
                         to reach a compromise solution that would meet  sored GERD talks carried out so far, and that it
                         the requirements of all three countries.  was confident that talks would resume.
                           They also renewed their appeal to the interna-  Meanwhile, Egyptian President Abdel Fattah
                         tional community, in Africa, the US and Europe,  el-Sisi has courted French support, stressing to
                         to prevent Ethiopia effectively presenting a fait  French President Emmanuel Macron that he is
                         accompli, the two countries said in a statement.  determined to preserve his country’s water rights
                           The statement follows Ethiopia’s announce-  to the River Nile.
                         ment at the start of May that it would again let   Sisi said that he would reach “legal” and “fair”
                         water flow into the GERD dam in the summer  agreement over the filling and operation of the
                         and begin power generation, even though there  GERD.
                         was no binding agreement governing the matter.  Ethiopia conducted its first filling in July 2020
                           Ethiopia intends to test two of the 6,475-MW  with 5bn cubic metres. The total capacity of the
                         hydro dam’s 16 planned turbines.     reservoir is 74 bcm, to be filled over several years.
                           Egypt and Sudan claim that Ethiopia is   The dam is anticipated to become the largest
                         undermining mediation efforts.       hydroelectric power station in Africa, with a pro-
                           Meanwhile, the US last week said it would  jected capacity of 6,500 MW, to meet the needs of
                         continue diplomatic efforts to find a solution for  Ethiopia’s 110mn people.™
                         the GERD.