       New coal supply





       issues hit India





        INDIA            JUST days after Indonesia permitted exports of  unloading System’, which uses hopper wagon
                         coal to resume, leading the wider coal-depend-  with bottom opening (BOBRN type)” in what
                         ent Asian region to breathe a sigh of relief, energy  some have seen as an apparent bid to attribute
                         generation plants in some of the more remote  any problems to rake loading and unloading
                         areas of India now face new struggles to secure  methods as opposed to any previously claimed
                         reliable supplies.                   bias in allocations.
                           This is proving increasingly problematic for   The usage of the term ‘foreign’ was then said
                         plants located further away from domestic coal  to refer to any coal deliveries moving outside
                         mines as the state-run Indian Railways looks to  home rail zones where supplies are typically
                         post despatch figures proving deliveries of coal  prioritised.
                         are back to normal.                    In the case of the Amravati plant, the lack of
                           It is not the first time Indian Railways has  a hopper unloading system was seemingly the
                         been accused of ‘bias’, however, with similar  reason behind the lack of coal at the site; “The
                         issues occurring at the end of summer, 2021,  unloading time of hopper rake is much less, i.e.,
                         although it is believed to be the first example of  three hours per rake, therefore has better turn
                         the busiest rail network in the world labelling  around. As a result, rake supply to these short-
                         some of the more remote drop-offs as ‘foreign’ in  er-distance plants dealing with faster circuit
                         a bid to restrict deliveries.        Hopper rake naturally improves,” Indian Rail-
                           In response to some of India’s private power  ways said.
                         suppliers highlighting the problems they are fac-  In India’s south-eastern state of Tamil Nadu,
                         ing with regional rail networks, the Ministry of  meanwhile, a trio of coal power plants are
                         Power in New Delhi launched an investigation  expected to remain starved of fuel as they near
                         asking Indian Railways for information of reme-  completion.
                         dial action being taken to alleviate issues in areas   In information released by the the Tamil
                         with seemingly less frequent deliveries.  Nadu Generation and Distribution Corporation
                           One case in point is the Maharashtra Amar-  (TANGEDCO) – the region’s state-owned elec-
                         avati power generation plant operated by Rattan  tricity producer – both Central and State govern-
                         India Power, which last week closed down one of  ment help has been requested in guaranteeing
                         its units as a result of lack of supply in the south-  supplies after a five-year coal excavation period
                         east central rail zone (SECR).       had expired on the back of administrative delays
                           Responding to calls from industry and the  by the central government.
                         Ministry of Power, the Ministry of Railways this   According to a senior TANGEDCO official,
                         week released details on how it intends to help  “The three new thermal stations, with a total
                         build stocks at remote power stations, referring  generation capacity of 3,440 MW, will need at
                         to the case in Maharashtra by stating “These  least 30,000 to 40,000 tonnes of additional coal
                         reports have claimed that the power plant oper-  every day,” even if the 2016-2021 excavation
                         ated by Rattan India Power Ltd in Maharashtra  agreement has now passed.
                         has also been shut down due to [a] coal short-  As a result, TANGEDCO is now having
                         age resulting from insufficient rake allotment  to source supplies from private companies,
                         by SECR. Dismissing these misleading media  although the possibility remains open that the
                         reports, the Ministry of Railways has issued  regional energy supplier may be able to seek
                         a clarification” following up with “In South-  an extension on its mining agreement due to
                         East central railways, there are a large number  an initial delay in clearance by India’s Ministry
                         of thermal power plants [TPPs] which have  of Environment, Forest and Climate Change
                         less coal stock as per new coal stocking norms.  (MoEFCC). “If the Centre doesn’t approve (the
                         Many of these shorter-distance plants have both  Chandrabilla) coal block quickly, TANGEDCO
                         mechanised unloading flexibility, namely the  will have to purchase the fuel from private enti-
                         ‘Tippler unloading system’, which uses an open  ties”, a spokesperson for the company said.™