Page 8 - AfrElec Week 15 2022
P. 8

AfrElec                                            COAL                                               AfrElec


       Zimbabwe’s new coal-fired





       power plant expected online





       by November 2022






         ZIMBABWE        CONSTRUCTION of two coal-fired electricity  November when we will do the unit handover.”
                         generating units in western Zimbabwe is at 84%   When both get online, they will add on to
                         completion, according to a local daily.   the 920MW that the existing Hwange Thermal
                           The China Exim Bank is funding the Hwange  Power Station is producing.  This will assist in
                         Thermal Power Station expansion project with a  easing the power shortage in the country.
                         $1.5bn loan and Sinohydro, also of China, is the   The Zimbabwe Power Company (ZPC)
                         contractor.                          said on its website it was generating a total of
                           The first 300MW unit is forecast to be online  1,205MW on April 12, less than the current
                         by November with the second one, of the same  summer demand of 1,400MW.  Electricity con-
                         capacity, by February 2023, according to a report  sumption rises to 1,800MW in winter, which
                         by The Chronicle, a state-owned daily on Tues-  falls between May and August.
                         day (April 12).                        Hwange Thermal Power Station was sending
                           Unit 7 is expected to be commissioned in  325MW to the grid on April 12 while Kariba
                         November 2022 while Unit 8 is expected to be  hydro was dispatching 880MW, according to
                         ready by February 2023.              ZPC. Three coal facilities in Harare, Bulawayo
                           urbines and generator sets at one unit have  and Munyati were all down.
                         been completed while the boiler is 93% com-  The supply gap is met by power imports from
                         plete, the paper reported, citing the project engi-  South Africa and Mozambique but, state-owned
                         neer Forbes Chanakira.               daily The Herald quoted the Zimbabwe Elec-
                           Engineers expect to do dynamic testing of  tricity Supply Authority’s executive chairman,
                         some of the sections this week paving the way for  Sydney Gata on March 17 saying the utility lacks
                         handover of the plant in November, with overall  foreign currency to keep up with installments.
                         progress now at 84.20%.              This forces the utility to maintain a load shed-
                           “Essentially, turbines and generator sets were  ding regime.
                         completed for Unit 7 and are awaiting com-  Chanakira said 810 of the 875 transmission
                         mencement of commissioning. The boiler is at  towers that must be erected to move the addi-
                         around 93% completion and for the coal stock-  tional electricity from Hwange to Bulawayo,
                         yard, we expect it to come on board in May,”  the country’s second-biggest city, have been
                         Chanakira is quoted as saying.       installed.
                           “The  distributed  control  system  that is   “A new 400kv line will be installed and run
                         responsible for controlling the boiler has been  parallel to the existing lines on the 368km stretch
                         switched on. We expect to start hot commis-  between Hwange and Bulawayo,” the paper said.
                         sioning end of July where we burn coal in the  The expansion project started in 2018 but was
                         boiler to heat steam. It will run all the way up to  hampered by the COVID-19 outbreak.  ™


























       P8                                       www. NEWSBASE .com                           Week 15   14•April•2022
   3   4   5   6   7   8   9   10   11   12   13