Page 10 - AsiaElec Week 07 2022
P. 10

AsiaElec                                      RENEWABLES                                             AsiaElec


       Sapura Energy issues termination





       notice to Yunneng Wind Power









        MALAYSIA         MALAYSIA’S Sapura Energy has issued a ter-  the contract in the best interest of the Group.”
                         mination notice to Yunneng Wind Power for a   Sapura Energy said it would pursue its claims
                         contract for the transportation and installation  using the dispute resolution process prescribed
                         of monopiles at the Yunlin offshore wind farm  in the contract, namely arbitration under the
                         in Taiwan.                           German Institution of Arbitration in Bremen.
                           The row centres on an alleged breach of con-  “As advised by external international counsels,
                         tract after delays in the work involved, which has  Sapura Energy has an immediate right to legally
                         been pushed back from 2020 to 2023.  and contractually terminate the contract,”
                           Sapura Energy’s subsidiary Sapura Offshore  Sapura Energy noted.
                         was awarded the contract in March 2019. Sapura   Sapura Energy installed the first monopile at
                         Energy said the project was initially expected to  the Yunlin project in October 2020. In August
                         be completed in September 2020, but this was  2021, Yunneng Wind Power said foundation
                         delayed to September 2023 because of unre-  installations for the Yunlin Offshore Wind Farm
                         solved technical and operational issues not  were “scheduled to be finalised in year 2021,”
                         attributable to Sapura Energy, which “signifi-  and that the Yunlin Offshore Wind Farm was
                         cantly altered the basis of the contract”.  expected to be fully installed and commissioned
                           “Negotiations with Yunneng to remedy  by the first quarter of 2022. The wind farm,
                         the breach began in November last year,” said  located about eight kilometres off the west coast
                         Sapura Energy Group CEO Anuar Taib. “Since  of Taiwan at Yunlin County, is expected to have
                         we exhausted all avenues for an amicable solu-  a total capacity of up to 640MW.%.
                         tion, we made the tough decision to terminate
















































       P10                                      www. NEWSBASE .com                       Week 07   16•February•2022
   5   6   7   8   9   10   11   12   13   14   15