Page 11 - EurOil Week 10 2021
P. 11

EurOil                                PIPELINES & TRANSPORT                                           EurOil










































       Nord Stream 2 could take until



       end-September to finish





        RUSSIA            CONSTRUCTION of Russia’s trouble-stricken  Nord Stream 2 is not all that surprising and not
                         Nord Stream 2 pipeline project is due to resume  critical to the business case of Gazprom, but
       Pipelaying had been   off Denmark later this month, the Danish Energy  nonetheless negative, moving a potential catalyst
       scheduled to resume   Agency has said, although the work could drag  for the stock from late spring until early autumn,”
       in Danish waters in the   for most of the year.        analysts at BCS Global Markets (GM) said in a
       middle of January.  Pipelaying had been scheduled to resume  research note.
                         in Danish waters in the middle of January, the   Nord Stream 2’s construction is proceed-
                         month after work was restarted off Germany.  ing despite the US’s sanctions regime, which
                         Construction ground to a halt at the end of  prompted Swiss contractor Allseas to with-
                         2019, after the US imposed its first sanctions on  draw from the project in December 2019.
                         the project.                         Additional sanctions imposed earlier this year
                           The Danish section of the pipeline between  and the looming threat of further ones have
                         Bornholm Island in the Baltic Sea and the Ger-  led a number of European contractors, equip-
                         man maritime border could take as long as the  ment suppliers and other companies to leave
                         end of September to complete, a notice published  the project.
                         by the Danish Maritime Authority has indicated.   Among them was Norway-based independ-
                         Previously completion had been anticipated in  ent certification body DNV GL, which halted its
                         April. Two Russian-flagged pipelaying vessels,  verification activities at Nord Stream 2. The Nord
                         Akademik Cherskiy and Fortuna, are operating  Stream 2 operator had hired DNV GL to “verify
                         in the area.                         the safety and technical integrity” of the project
                           A further 110 km of pipe needs to be laid off   and to issue a certificate of compliance upon its
                         Denmark and 28 km in German waters, accord-  “satisfactory completion.”
                         ing to the Nord Stream 2 operating company,   Third-party certification, confirming that
                         a wholly owned subsidiary of Russia’s state-  Nord Stream 2 was designed, fabricated, installed
                         owned Gazprom. After pipelaying is finished,  and commissioned in accordance with “applica-
                         the project will require above-water tie-ins of  ble technical, quality and safety requirements, is
                         unconnected pipe sections, as well as design  needed before the DEA can grant a 'certification
                         verification.                        of conformity,' enabling pipeline commissioning
                           “The delay in the physical completion of  to start.” ™



       Week 10   11•March•2021                  www. NEWSBASE .com                                             P11
   6   7   8   9   10   11   12   13   14   15   16