               Province    Refinery          Status     Current Nameplate Capacity (bpd)  Nameplate Capacity Addition (bpd)  Total (bpd)
               East Azarbaijan  Tabriz Shahriar                        110,000             5,000      115,000
               Hormozgan   Bahman Geno - Bandar Abbas  Under Construction  0              300,000     300,000
               Hormozgan   Bandar Abbas                                344,000                        344,000
               Hormozgan   Morvarid Makran - Jask  Under Construction     0               300,000     300,000
               Hormozgan   Lavan Island                                60,000             150,000     210,000
               Kermanshah  Anahita           Under Construction           0               150,000     150,000
               Kermanshah  Kermanshah                                  22,000              3,000       25,000
               Khuzestan   Abadan                                      360,000             40,000     400,000
               Khuzestan   Arvand - Khuzestan Super Heavy              120,000                        120,000
               Markazi     Arak - Imam Khomeini Shazand                170,000             80,000     250,000
               Qeshm       Qeshmi            Under Construction           0                68,000      68,000
               Shiraz      Shiraz (Pars)                               82,000                          82,000
               Tehran      Isfahan                                     200,000            170,000     370,000
               Tehran      Tehran                                      245,000                        245,000
               Total Oil                                              1,713,000          1,266,000   2,979,000
               Bushehr     Siraf (8 units - 60,000 bpd each)  Under Construction  0       480,000     480,000
               Hormozgan   Persian Gulf Star (PGSR)                    400,000             50,000     450,000
               Khuzestan   Shahid Ghasem Soleimani  Under Construction    0               300,000     300,000
               Shiraz      Shiraz Pars Farayand  Under Construction       0               120,000     120,000
               Total Condensate                                        400,000            950,000    1,350,000
               Total                                                  2,113,000          2,216,000   4,329,000
               Source: IGM Energy


                         and the second phase seen raising this to 55,000-  Soleimani condensate refinery at the Bandas
                         60,000 bpd.                          Abbas downstream hub in the same province.
                           Owji added: “In the downstream sector, we   Bank Meli Iran, Tejarat Bank and Refah
                         reached an agreement with Gazprom to build  Bank signed deals with the downstream focused
                         gas transmission and export pipelines to coun-  National Iranian Oil Refining and Distribu-
                         tries such as Oman and Pakistan.”    tion Co. (NIORDC), Persian Gulf Petrochem-
                           Meanwhile, he was quoted by the Ministry  ical Industries Co. (PGPIC), Ahdaf Investment
                         of Petroleum’s (MoP) Shana news network as  Group and Tadbir Energy Development Group
                         saying: “We have also signed 28 contracts with  covering $11.1bn in investment in the Shahid
                         a total value of over $1bn for collecting flare  Ghasem Soleimani unit, while Bank Mellat, Par-
                         gas, most of which have been signed with pri-  sian Bank and Mofid Economic Group agreed to
                         vate companies that will use the collected gas as  provide $6.7bn for Morvarid Makran.
                         payment.”                              The report noted that the Soleimani facility’s
                           As has been common during the first 12  slate would be comprised of fuels (65%) and pet-
                         months of President Ebrahim Raisi, Owji cast  rochemicals (35%), with both projects scheduled
                         blame for a lack of progress on sanctions and the  to be completed within five years.
                         previous administration. “At the beginning of   Jask has become an area of focus for Iran in
                         the 13th administration, there were 48 half-com-  the last 18 months or so. Following the commis-
                         pleted projects worth $13bn in the Ministry of  sioning of the Goreh-Jask Crude Oil Transfer
                         Petroleum, which were followed up strongly  Project – a 1,000-km pipeline connecting pro-
                         afterwards,” he said.                duction from Khuzestan with the Sea of Oman –
                           However, he said that the final upstream  plans were announced for 10mn barrels of crude
                         phase of South Pars – Phase 11 – would “become  storage. The port also comprises the 350,000 bpd
                         productive soon once Platform 12C of Phase 12  export/import Jask Oil Terminal (JOT).
                         of the field is installed at the location of Plat-  Downstream MEA (DMEA) understands
                         form 11B before the end of the current Iranian  that 10mn barrels will be added in each phase
                         calendar year”, with three refining trains to be  to reach a total storage capacity of 30mn barrels.
                         launched at the remaining downstream Phase   The Goreh-Jask pipeline’s 300,000 bpd first
                         14 refining site during the same period.  phase was completed in May 2021 and consists
                                                              of 1,000-km of 42-inch (1,067-mm) pipe run-
                         Downstream                           ning from the Goreh oil terminal in Bushehr
                         Tehran’s expansion plans also extend into the  Province to Jask.
                         downstream, with Owji noting that “by the end   Phase 2 is also underway, which will expand
                         of this year, several petrochemical projects, such  the capacity of the line to carry than 1mn bpd
                         as Hengam petrochemical plant, worth about  of crude from the oilfields in the West Karoun
                         $2.6bn, will also come on stream.”   cluster via the Omidieh pumping station. The
                           Meanwhile, IRNA reported that a group of  wider pipeline project will include five pump-
                         domestic firms have signed MoUs with major  ing stations, two pigging stations and terminals.
                         Iranian banks to fund the development of  The pipeline project is reported to have come in
                         two 300,000 bpd refineries in the south of the  under budget at $1.1bn.
                         country.                               While there remains uncertainty about the
                           Both Raisi and Owji attended a signing cer-  likelihood of whether all of its ambitious projects
                         emony on August 1 during which the banks  will react fruition, there is a broad sense of opti-
                         pledged to provide $17.8bn for the construction  mism about Iran’s oil and gas sector development
                         of the Morvarid Makran refinery (previously  and as negotiations in Vienna resume, the coun-
                         referred to at Hormuz refinery) the port of Jask  try is ready to take advantage of any concessions
                         in Hormozgan Province and the Shahid Ghasem  made by its Western counterparts.™



       Week 31   04•August•2022                 www. NEWSBASE .com                                              P5
   1   2   3   4   5   6   7   8   9   10