AsianOil                                       SOUTH ASIA                                            AsianOil


       McDermott announces delivery of U-Field




       for ONGC’s KG-DWN 98/2 Block




        PROJECTS &       MCDERMOTT International announced on  India in the last 18 months,” stated McDermott’s
        COMPANIES        March 23 that it had navigated challenges includ-  senior vice-president for Asia-Pacific, Mahesh
                         ing the coronavirus (COVID-19) pandemic and  Swaminathan. “The company’s diverse fleet
                         an active monsoon season to deliver the U-Field  brought significant efficiencies and achieved
                         gas project offshore India.          notable firsts during the offshore campaign. This
                           The project is part of state-owned Oil and Nat-  campaign marked the first use of pipe-in-pipe
                         ural Gas Corp.’s (ONGC) KG-DWN 98/2 Block  insulation technology in an offshore India pro-
                         development in the Bay of Bengal off India’s east  ject. The LV105 also installed the first pipe-in-
                         coast. In its statement, McDermott described  pipe production flowline in India as part of this
                         KG-DWN 98/2 as “the largest and one of the  campaign,” Swaminathan added.
                         most complex subsea projects in Asia-Pacific,”   “The opening of the U1-B (GX-06) well in the
                         involving extensive subsea infrastructure instal-  DWN-98/2 Block is a major milestone that we can
                         lation in ultradeep waters.          all be immensely proud of,” said L&T HE’s CEO
                           McDermott has been tasked with delivering  and managing director, Subramanian Sarma,
                         two gas systems for the U-Field and R-Field at  who also serves as whole-time director and senior
                         the block, while Larsen & Toubro Hydrocarbon  executive vice-president of energy at L&T. “That
                         Engineering (L&T HE) is in charge of manufac-  we managed to achieve this despite extremely dif-
                         turing the structures for the project.  ficult project terrain and weather conditions even
                           The U-Field is now connected to ONGC’s  as a global pandemic raged on, speaks volumes of
                         Vashishtha subsea infrastructure, McDermott  the resolve of the project teams.”
                         said. The company also noted its work on that   The DWN-98/2 Block is expected to signifi-
                         piece of infrastructure.             cantly increase India’s gas production upon com-
                           “This is the fourth gas production milestone  pletion, helping to reduce the country’s reliance
                         McDermott has delivered on the east coast of  on imports.™


       ONGC commissions water injection




       platform at Mumbai High




        PROJECTS &       INDIA’S Oil and Natural Gas Corp. (ONGC) has   Days after the announcement about the facil-
        COMPANIES        commissioned a new water injection platform at  ity’s start-up, India’s Comptroller and Auditor
                         its Mumbai High project off the country’s west  General (CAG) said the country had lost 3.8mn
                         coast.                               tonnes (27.9mn barrels) of oil over four years
                           The company announced on its social media  as a result of ONGC’s water injection projects
                         channels on March 19 that the WIS-R platform  off the west coast not hitting their targets. The
                         had been commissioned as part of the Mumbai  lost barrels, identified for the audit period from
                         High Phase IV redevelopment. The facility is  2014-15 to 2018-19, are estimated to be worth
                         expected to help boost production from the field  INR112.76bn ($1.48bn).
                         via low-salinity water injection.      Mumbai High was identified as one of the
                           The water injection platform was built by  fields where water injection was required as
                         Larsen & Toubro (L&T), and has a processing  production declines, along with the Neelam and
                         capacity of 350,000 barrels per day (bpd) of  Heera fields.
                         water. The low-salinity water injection sys-  The CAG cited ageing injection infrastruc-
                         tem incorporated into the project is reported  ture, frequent pipeline leakages owing to the
                         to be the first of its kind for ONGC and has  poor quality of injection water, non-implemen-
                         the capacity to handle up to 125,000 bpd of  tation of feasibility report inputs and, to some
                         water.                               extent, production from wells with a high gas-
                           L&T was awarded the engineering, procure-  oil ratio as having played a role in the underper-
                         ment, construction and installation (EPCI)  formance of water injection projects.
                         contract for the facility in 2019. The platform is   The CAG said this loss could not be consid-
                         linked to existing water injection infrastructure  ered as deferred production but rather a perma-
                         at Mumbai High.                      nent loss of oil.™