Page 12 - AfrOil Week 08 2022
P. 12

AfrOil                                 PROJECTS & COMPANIES                                            AfrOil



                         The Australian company stressed, though, that
                         it was still mapping the deeper-lying reservoirs
                         of the Bambo-1 and Bambo-1ST1 wells and
                         conducting laboratory analysis of samples col-
                         lected during the drilling programme. It did
                         not say when it expected these processes to be
                         completed.
                           However, it did state that it was looking to
                         being another partner on board. In its statement,
                         FAR explained that it intended to farm down its
                         interest in Blocks A2 and A5, which it is explor-
                         ing and developing under the same licence, to
                         another company that could help carry the cost
                         of drilling another exploration well in late 2023
                         and making up some of its own past costs.
                           It did not name any potential investors, but
                         it did indicate that it was close to reaching an   Panthera, Jatta and Malo are new prospects at Blocks A2 (Image: FAR Ltd)
                         agreement with its current partner Petronas
                         (Malaysia) on reducing this year’s expenditures   Equity in Blocks A2 and A5 is split 50:50
                         from $9.56mn to $5.7mn, a cut of 40%. The two   between FAR and Petronas, with the former
                         companies are looking to cut costs by revising   acting as operator. The Australian company
                         their work programme.                secured its licence for the blocks in 2017. ™


       Eiffage finishes all 21 caissons




       for FLNG breakwater at GTA field






        SENEGAL/MAURITANIA  EIFFAGE Genie Civil (France) has finished   which is about 10 km distant from the shore.
                         building all 21 of the large caissons that will be   More than 1,700 workers participated in
                         used to form a breakwater protecting the float-  the construction of the caissons, which weigh
                         ing LNG (FLNG) vessel installed at the Greater   16,000 tonnes each, Eiffage said. Each of the
                         Tortue/Ahmeyim (GTA) natural gas field off-  units measures 28 metres wide, 32 metres high
                         shore Senegal and Mauritania.        and 55 metres long.
                           The French engineering company said in a   The French company is working together
                         statement that it had constructed the 21 cais-  with Saipem (Italy) to provide engineering,
                         sons in the Senegalese capital of Dakar, using   procurement and construction (EPC) services
                         more than 130,000 cubic metres of cement from   related to the marine hub and terminal for the
                         two of its own factories. To date, it said, 16 of   LNG component of the GTA project. The part-
                         the units have already been taken out to the field   ners won the contract from BP, the UK-based
                         and installed at the future site of the breakwater,   operator of the offshore field, in 2019.
























                                                     Rendering of breakwater structure at GTA LNG facility (Image: Eiffage)



       P12                                      www. NEWSBASE .com                       Week 08   23•February•2022
   7   8   9   10   11   12   13   14   15   16   17